PMO dashboardSaudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORMCommand center

Live· Updated just now

Executive operations room

The enterprise portfolio as it moves: strategy, major projects, risks, budget and decisions.

--:--:--

17 Jumada I 1448 AH

28 October 2026

Projects

36

⁦18⁩ on track · ⁦6⁩ delayed or critical

Progress

⁦52%⁩

Planned ⁦57%⁩

Spent to date

SAR 2.4B

of SAR 5.2B (⁦47%⁩)

Estimate at completion

SAR 5.6B

Forecast overrun SAR 407.7M

Performance indices

0.85SPI0.93CPI

Needs attention

18high risks9decisions

Open high risks · decisions and gates waiting

Strategy

Selected KPIs

  • Premises and centre projects delivered to plan73%
  • SCA systems hosted in the cloud47%
  • SCA centres operating in owned buildings43%
  • Approved budget executed77%

Project map

Pick a region or a project
Riyadh · 24Makkah · 2MadinahEastern · 2Qassim · 2Asir · 2Tabuk · 1Hail · 1Northern Borders · 1JazanNajranAl-BahaAl-Jouf · 1SCA Headquarters, Riyadh
  • On track18
  • At risk10
  • Off track4
  • Critical2
  • On hold2

Major projects

Off trackPRJ-2026-002

SCA Headquarters, Riyadh

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Progress⁦42%⁩

⁦42%⁩
Budget
SAR 1.2B
EAC
SAR 1.3B
Forecast slip
⁦74⁩ days
Region
Riyadh
SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93⁦88%⁩ chance of slipping within ⁦60⁩ days
Open the project workspace

Off track

Critical risks

18
  • 25Main contractor cash-flow distress and unpaid subcontractorsAl-Khobar Branch — Rehabilitation & ExtensionSAR 36M
  • 20Steel and concrete price rises driving price-adjustment claimsSCA Headquarters, RiyadhSAR 48M
  • 20Contractor financial claims piling up over unapproved variationsSCA Academy Campus, RiyadhSAR 41M
  • 20Late handover of the northern plot and utility diversions in zones 3 and 4SCA Headquarters, RiyadhSAR 31M
  • 20Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Qassim Vocational Qualification CentreSAR 27M

Budget by portfolio

  • Digital Services & Platforms PortfolioSAR 183.9M

  • Academy & Qualification Centres PortfolioSAR 1.5B

  • Technology & Enterprise Systems PortfolioSAR 376M

  • Building Rehabilitation & Sustainability PortfolioSAR 726M

  • Headquarters & Regional Centres PortfolioSAR 2.8B

  • Institutional Excellence & Governance PortfolioSAR 30.5M

  • Bar: spent · tick: budget · figure: EAC

Decisions needed

9
  • ⁦26⁩ h lateApprove the October Steering Committee minutes
  • ⁦22⁩ h leftPay subcontractors directly on the Al-Khobar branch rehabilitation & extension
  • ⁦50⁩ h leftRefer the SCA Academy campus contractor’s claims to arbitration
  • ⁦96⁩ h leftApprove the updated corrective plan for Muqawil Release 4
  • ⁦140⁩ h leftRelease SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handover
Decide on the executive dashboard
LIVE
  1. 10:42New escalation: five foundation axes to redesign — Qassim qualification centre
  2. 10:15Certificate 27 approved on the SCA headquarters — SAR 31.6M
  3. 09:5014 SCA buildings and centres now connected to solar
  4. 09:20Nafath / Government Service Bus integration risk raised to 16
  5. 08:40Contractor satisfaction with digital services updated: 74% (+2 pts)