The objective’s weakest KPI, “SCA services fully available online”, is at 86% of its target, and its heaviest project, “Muqawil Platform — Release 4”, is At risk. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the Nafath integration in Muqawil with a dedicated integration squad
Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030·h.alqurashi@sca.saDue 2026-10-226 days overdue2026-10-22·11 Jumada I 1448 AHK-1.1.1Muqawil Platform — Release 4
Overdue
Fix the five biggest complaints in the Muqawil journey, starting with re-keyed commercial-register data
Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005·s.alghamdi@sca.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHK-1.1.1Muqawil Platform — Release 4
In progress
Ship 6 priority contractor e-services before year end in an interim release
Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003·f.alshehri@sca.saDue 2026-12-20In 53 days2026-12-20·11 Rajab 1448 AHK-1.1.2Muqawil Platform — Release 4
Open
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
Satisfaction has been flat at 74% since August; top complaints are slow Nafath integration and re-keying commercial-register data.
Eng. Reem K. Al-Dosari · 2026-10-22
Challenge
Muqawil Release 4 is 42 days behind baseline, delaying 18 e-services planned for this year.
Faisal A. Al-Shehri · 2026-10-19
Note
The digital transformation committee put the membership certificate and membership transfer first in the next release.