Change requests, their impact analysis and the CCB approval path.
of 16 this year
meeting 42 — tomorrow
all open requests
extra days on projects
worth SAR 75M
29 October 2026 · 13:00Meeting Room 3 — 5th floor
Agenda
From submission to the approval decision — click a stage to filter the list
Cost impact by kind of change
All requests this year
SAR 137.5M
Total
Every request is routed by its kind and impact level; this is the rule the route reads.
| Kind of request | MinorUp to SAR 1M and no extra days | ModerateUp to SAR 5M and 90 days | MajorAbove SAR 5M or 90 days |
|---|---|---|---|
| Scope |
|
|
|
| Budget |
|
|
|
| Schedule |
|
|
|
| Deliverables |
|
|
|
| Contract |
|
|
|
| Resources |
|
|
|
Any change to scope, budget, schedule, deliverables, contract or resources comes through here.
Display options
| Muqawil Platform — Release 4 | Resources | +SAR 980K | −12 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | 2026-10-26 | In 12 days2026-11-0929 Jumada I 1448 AH | 0/6 | Submitted | |
| Muqawil Platform — Release 4 | Contract | +SAR 1.2M | None | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | 2026-10-20 | In 6 days2026-11-0323 Jumada I 1448 AH | — | Submitted | |
CR-2026-014 Re-route the network in Al-Rawdah district | Secure Enterprise Network | Scope | +SAR 1.2M | +20 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | 2026-10-19 | In 5 days2026-11-0222 Jumada I 1448 AH | — | Submitted |
| Muqawil Platform — Release 4 | Scope | +SAR 1.9M | +21 d | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa | 2026-10-15 | Due tomorrow2026-10-2918 Jumada I 1448 AH | 4/6 | In review | |
| SCA ERP System | Budget | +SAR 6.8M | +45 d | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | 2026-10-09 | In 2 days2026-10-3019 Jumada I 1448 AH | 2/6 | In review | |
| Jeddah Branch & Qualification Centre | Scope | +SAR 22.5M | +75 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-10-06 | 1 day overdue2026-10-2716 Jumada I 1448 AH | 0/6 | Submitted | |
CR-2026-006 Extend the contract by 150 days | SCA Academy Campus, Riyadh | Schedule | — | +150 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | 2026-10-01 | 6 days overdue2026-10-2211 Jumada I 1448 AH | 0/6 | In review |
CR-2026-010 Redesign the foundations of axes 12 to 16 | Qassim Vocational Qualification Centre | Scope | +SAR 8.4M | +55 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | 2026-09-28 | 9 days overdue2026-10-198 Jumada I 1448 AH | 4/6 | In review |
| Muqawil Mobile App — Release 3 | Deliverables | +SAR 320K | +10 d | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa | 2026-09-14 | 2026-09-282026-09-2817 Rabiʻ II 1448 AH | 6/6 | Deferred | |
CR-2026-005 Variation 7: revise the central HVAC system | SCA Academy Campus, Riyadh | Contract | +SAR 18.6M | +40 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | 2026-08-20 | 55 days overdue2026-09-0321 Rabiʻ I 1448 AH | 6/6 | Escalated |
CR-2026-015 Add a classified-correspondence module | Correspondence & Document Management System (DMS) | Deliverables | +SAR 650K | +30 d | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | 2026-08-11 | 2026-08-252026-08-2512 Rabiʻ I 1448 AH | 6/6 | Rejected |
CR-2026-013 Replace the cooling-unit supplier | SCA Backup Data Centre | Contract | +SAR 3.1M | +14 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | 2026-05-17 | 2026-05-312026-05-3114 Dhuʻl-Hijjah 1447 AH | 6/6 | Approved |
CR-2026-011 Redesign training halls for e-testing | Jeddah Branch & Qualification Centre | Scope | +SAR 9.6M | +20 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-04-12 | 2026-04-262026-04-269 Dhuʻl-Qiʻdah 1447 AH | 6/6 | Approved |
| SCA Headquarters, Riyadh | Scope | +SAR 38.5M | +60 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | 2026-03-02 | 2026-03-232026-03-234 Shawwal 1447 AH | 6/6 | Approved | |
| Muqawil Platform — Release 4 | Scope | +SAR 2.4M | +18 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | 2026-02-10 | 2026-02-242026-02-247 Ramadan 1447 AH | 6/6 | Approved | |
CR-2026-003 Add an e-test hall wing | Al-Khobar Branch — Rehabilitation & Extension | Scope | +SAR 21.4M | +45 d | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | 2026-01-18 | 2026-02-082026-02-0820 Shaʻban 1447 AH | 6/6 | Approved |