CR-2026-010Qassim Vocational Qualification Centre

Redesign the foundations of axes 12 to 16

ScopeIn reviewImpact level: Major9 days overdue2026-10-198 Jumada I 1448 AH

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 8.4M

Current budgetSAR 345M

After the changeSAR 353.4M

+2.4%

Schedule

+⁦55⁩ d
  • Baseline finish2027-05-31
  • New finish2027-07-25

Benefits

0%

No effect on benefits

⁦0⁩% of expected benefits

Reason for change

Unforeseen ground at axes 12 to 16

Justification

The current design misses the required safety factor

PMO recommendation

Approve

The PMO recommends urgent approval: every day of delay costs SAR 150K

Approval workflow

  1. Submitted

    Eng. Ahmed Y. Asiri

    Done2026-09-28

  2. PM review

    Eng. Ahmed Y. Asiri

    Done2026-09-29

  3. Impact analysis

    Karim Haddad

    Done2026-10-03

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-10-04

  5. Project owner’s acceptance

    Eng. Bandar M. Al-Shammari

    Done2026-10-04

  6. 6

    Change committee recommendation

    Dr. Mohammed I. Al-Subaie

    Now2026-10-29

  7. 7

    Executive Committee decision

    Dr. Abdullah S. Al-Qahtani

    Later

  8. 8

    Baseline updated

    Eng. Ahmed Y. Asiri

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SAR 5M or 90 days

  • A cost impact of SAR 8.4M is above SAR 5M — «major»: the Change Committee recommends and the Executive Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting Room 3 — 5th floor
  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairNot voted
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saNot voted
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove
4/6Quorum met
  • Approve4
  • Approve with conditions0
  • Reject0
  • Abstain0

Quorum met · Awaiting the change committee’s decision in meeting ⁦42⁩