CR-2026-010Qassim Vocational Qualification Centre
Redesign the foundations of axes 12 to 16
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 8.4MCurrent budgetSAR 345M
After the changeSAR 353.4M
+2.4%
Schedule
+55 d- Baseline finish2027-05-31
- New finish2027-07-25
Risk
−12Treats the centre’s critical risk
Benefits
0%No effect on benefits
0% of expected benefits
Reason for change
Unforeseen ground at axes 12 to 16
Justification
The current design misses the required safety factor
PMO recommendation
ApproveThe PMO recommends urgent approval: every day of delay costs SAR 150K
Approval workflow
Submitted
Eng. Ahmed Y. Asiri
Done2026-09-28
PM review
Eng. Ahmed Y. Asiri
Done2026-09-29
Impact analysis
Karim Haddad
Done2026-10-03
Finance & procurement
Munirah A. Al-Khalidi
Done2026-10-04
Project owner’s acceptance
Eng. Bandar M. Al-Shammari
Done2026-10-04
- 6
Change committee recommendation
Dr. Mohammed I. Al-Subaie
Now2026-10-29
- 7
Executive Committee decision
Dr. Abdullah S. Al-Qahtani
Later
- 8
Baseline updated
Eng. Ahmed Y. Asiri
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMajorAbove SAR 5M or 90 days
- A cost impact of SAR 8.4M is above SAR 5M — «major»: the Change Committee recommends and the Executive Committee decides.
- It has a financial link, so Finance & Procurement take part before the decision.
- It changes scope or deliverables, so the project owner must accept it.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairNot voted
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saNot voted
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove
- Approve4
- Approve with conditions0
- Reject0
- Abstain0
Quorum met · Awaiting the change committee’s decision in meeting 42