Procurement

The procurement plan: packages, methods, evaluation and award.

Working on:Saudi Contractors Authority
Packages in the plan
18

FY2026: ⁦14⁩ · FY2027: ⁦4⁩

Estimated value
SAR 787M

FY2027 plan: SAR 145.4M

In the market now
8

SAR 529.8M

Awaiting award
3

With the procurement committee

Award savings
SAR 600K

⁦7.1%⁩ below estimate

Procurement timeline

Bars: planned spans of each step; diamonds: actual dates; gold line: today

Package
2025 Oct  2026Jan   Apr   Jul   Oct  2027Jan   Apr   Jul  
Prepare booklet Issue Bids close Evaluate Award Actual date Today

Etimad integration

The data is ready to exchange with Etimad; the live link starts once the permissions and interfaces are granted.

Integration-ready for Etimad

The integration layer is in place; data exchange starts once the permissions and interfaces are granted.

  • Tender, bid and award fields mapped to the Etimad data model
  • An Etimad reference kept for every published package
  • Awards linked to contracts and certificates in Munjaz
  • Awaiting the interface permissions from the competent authority
  • Awaiting the integration interfaces for automatic sync

References ready to sync

Packages with an Etimad reference: ⁦10⁩

  • Asir vocational qualification centre — main works260614031187Awaiting link
  • Asir vocational qualification centre — supervision260705031244Awaiting link
  • Contractor files & building-permit archive — scanning and automated indexing services261004031302Awaiting link
  • Identity & access management licences260914031355Awaiting link
  • SCA strategy refresh & execution plans advisory260224030418Awaiting link
  • Irtiqaa portal development & contractor capability assessment251006029877Awaiting link
  • SCA Academy — qualification programmes & professional tracks provider261012031366Awaiting link