Design a report without code: columns, filters, groups and charts.
Shown by your permissionsProject Management Office: 36 projects — everything in your scope
Filters
Health
Portfolio
More than 30 days late
Group by
Chart
Measure
KPI tiles on top
Columns
Drag to reorder, or use the arrows.
Live preview · Projects
Refreshed from system data on every change.
Budget · Portfolio
| Name | Portfolio | Budget | Progress | Slip (days) | Health |
|---|---|---|---|---|---|
| Headquarters & Regional Centres Portfolio (8) | |||||
| SCA Headquarters, Riyadh | Headquarters & Regional Centres Portfolio | SAR 1.2B | 42% | +74 | Off track |
| Smart Test-hall Proctoring & Access Control | Headquarters & Regional Centres Portfolio | SAR 74M | 79% | +45 | At risk |
| Secure Enterprise Network | Headquarters & Regional Centres Portfolio | SAR 132M | 55% | +33 | At risk |
| Qassim Vocational Qualification Centre | Headquarters & Regional Centres Portfolio | SAR 345M | 44% | +64 | Off track |
| Asir Vocational Qualification Centre | Headquarters & Regional Centres Portfolio | SAR 520M | 2% | 0 | On track |
| Electronic Skills-test Halls — Makkah Region | Headquarters & Regional Centres Portfolio | SAR 46M | 2% | 0 | On track |
| Unified Operations Centre for Centres & Platforms | Headquarters & Regional Centres Portfolio | SAR 110M | 0% | 0 | On track |
| Arar Vocational Qualification Centre | Headquarters & Regional Centres Portfolio | SAR 238M | 33% | +28 | At risk |
| Total | SAR 2.6B | ||||
| Academy & Qualification Centres Portfolio (4) | |||||
| Jeddah Branch & Qualification Centre | Academy & Qualification Centres Portfolio | SAR 286M | 39% | +95 | Off track |
| SCA Academy Campus, Riyadh | Academy & Qualification Centres Portfolio | SAR 640M | 57% | +152 | Critical |
| Hail Vocational Qualification Centre | Academy & Qualification Centres Portfolio | SAR 158M | 52% | +12 | At risk |
| Wadi Al-Dawasir Vocational Qualification Centre | Academy & Qualification Centres Portfolio | SAR 210M | 2% | +184 | On hold |
| Total | SAR 1.3B | ||||
| Building Rehabilitation & Sustainability Portfolio (5) | |||||
| Al-Khobar Branch — Rehabilitation & Extension | Building Rehabilitation & Sustainability Portfolio | SAR 412M | 68% | +126 | Critical |
| Solar Power for SCA Buildings & Centres | Building Rehabilitation & Sustainability Portfolio | SAR 96M | 58% | -8 | On track |
| Al-Jouf Training Centre Rehabilitation | Building Rehabilitation & Sustainability Portfolio | SAR 42M | 36% | 0 | On track |
| Energy Retrofit of Existing SCA Buildings (ESCO) | Building Rehabilitation & Sustainability Portfolio | SAR 33M | 8% | +123 | On hold |
| Khamis Mushait Training Centre Rehabilitation | Building Rehabilitation & Sustainability Portfolio | SAR 67M | 97% | +12 | On track |
| Total | SAR 650M | ||||
| Technology & Enterprise Systems Portfolio (7) | |||||
| SCA ERP System | Technology & Enterprise Systems Portfolio | SAR 64.5M | 61% | +58 | Off track |
| SCA Backup Data Centre | Technology & Enterprise Systems Portfolio | SAR 148M | 72% | +38 | At risk |
| SCA Cybersecurity Programme | Technology & Enterprise Systems Portfolio | SAR 38.6M | 88% | -5 | On track |
| SCA Systems Migration to the Cloud | Technology & Enterprise Systems Portfolio | SAR 52M | 47% | +21 | At risk |
| Mimar — Unified Building Journey & Government Integration | Technology & Enterprise Systems Portfolio | SAR 24M | 6% | 0 | On track |
| Correspondence & Document Management System (DMS) | Technology & Enterprise Systems Portfolio | SAR 14.2M | 95% | +46 | At risk |
| HR Self-Service | Technology & Enterprise Systems Portfolio | SAR 11.4M | 100% | -9 | On track |
| Total | SAR 352.7M | ||||
| Digital Services & Platforms Portfolio (7) | |||||
| Wifaq Dispute Settlement Platform — Release 2 | Digital Services & Platforms Portfolio | SAR 18.4M | 91% | -4 | On track |
| Muqawil Platform — Release 4 | Digital Services & Platforms Portfolio | SAR 86.4M | 58% | +42 | At risk |
| Muqawil Mobile App — Release 3 | Digital Services & Platforms Portfolio | SAR 12.6M | 64% | -3 | On track |
| Contracting Sector Information Centre & Data Governance | Digital Services & Platforms Portfolio | SAR 21.5M | 62% | +18 | At risk |
| Project Tracking Platform — National Phase | Digital Services & Platforms Portfolio | SAR 28M | 1% | 0 | On track |
| Electronic Model Contracts | Digital Services & Platforms Portfolio | SAR 8.2M | 100% | +20 | On track |
| Future Projects Forum 2027 | Digital Services & Platforms Portfolio | SAR 5.2M | 0% | 0 | On track |
| Total | SAR 180.3M | ||||
| Institutional Excellence & Governance Portfolio (5) | |||||
| Institutional Performance Measurement & KPI Dashboard | Institutional Excellence & Governance Portfolio | SAR 9.8M | 76% | -7 | On track |
| Irtiqaa Portal — Release 2 | Institutional Excellence & Governance Portfolio | SAR 6.4M | 63% | +31 | At risk |
| SCA Strategy Refresh & Execution Plans | Institutional Excellence & Governance Portfolio | SAR 3.2M | 70% | 0 | On track |
| SCA Academy — Learning Platform & Professional Tracks | Institutional Excellence & Governance Portfolio | SAR 7.5M | 4% | 0 | On track |
| Enterprise Risk & Business Continuity Framework | Institutional Excellence & Governance Portfolio | SAR 3.6M | 100% | 0 | On track |
| Total | SAR 30.5M | ||||