AI insight
74% chance Muqawil Platform — Release 4 slips within 45 days
The project is At risk today, but the SPI trend, the task-closure rate and the open risks point to a further slip.
Good morning, Dr. Noura M. Al-Otaibi17 Jumada I 1448 AH — 28 October 2026
Answers built on 36 projects updated up to today — every figure leads to its detail.
Update compliance, deliverables accepted on time, schedule variance, risks and impediments, and benefits realisation — open any one to see what is behind it.
Shown by your permissionsProject Management Office: 36 projects — everything in your scope
The health of the enterprise portfolio today, and where the trouble sits.
Budget-weighted across eight dimensions: schedule, cost, risk, scope, quality, resources, stakeholders and benefits.
66
/ 100
since January
Progress
52%
Planned 57%
SPI
0.85
CPI 0.93
Projects by status
Pick a portfolio to drill into its programmes and projects.
The six largest projects by budget — 66% of the whole portfolio.
Lateness is not one number — these are its root causes, ranked by days of delay.
Forecast delay of active projects, in days, grouped by primary cause.
Unapproved variations piling up into financial claims and extension requests.
Schedule and cost performance trend
Budget-weighted, January – October 2026
AI insight
The project is At risk today, but the SPI trend, the task-closure rate and the open risks point to a further slip.
Spend to date, what is committed, and the forecast cost to completion.
47% of budget
75%
7.9% over budget
Where does the overrun come from?
EAC minus budget for each portfolio (red is overrun) · SAR M
Monthly spend, 2026
Planned against actual, with the forecast to December · SAR M
0.93
Watch
CPI
0.85
Off track
SPI
Decisions waiting for your signature, and the risks that could change the picture.
By decision date. You can remind the decision owner.
The minutes hold 7 decisions and 12 actions; follow-up cannot start before approval.
Three subcontractors stopped work 19 days ago over unpaid dues from the main contractor; the new training and test hall wing is idle.
SAR 96M of claims over unapproved variations; the dispute board reached no settlement.
The plan recovers 30 of the 42 days by adding an integration squad for four months and resequencing wave 2.
Zones 3 and 4 of the HQ site wait on the northern plot handover and utility diversions; every month of delay costs SAR 6.8M.
Open risks scoring 15 or more (probability × impact).
Are the projects moving the targets? Strategic objectives and benefits realised.
Actual achievement against the 2026 target, per objective.
A Unified Reference for Regulating the Sector
A Cornerstone of Sector Development
Specialised, Value-adding Services
Value realised against value planned to date, by portfolio.
Total expected value
SAR 8.4B
Planned to date
SAR 661M
Realised
SAR 471.5M
71% of plan