Saudi Contractors AuthorityMunjaz11My actionsNotifications

Good morning, Dr. Noura M. Al-Otaibi17 Jumada I 1448 AH — 28 October 2026

Five questions for this morning

Answers built on ⁦36⁩ projects updated up to today — every figure leads to its detail.

Working on:Saudi Contractors Authority

The five indicators of the spec

Update compliance, deliverables accepted on time, schedule variance, risks and impediments, and benefits realisation — open any one to see what is behind it.

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

01Where are we?

The health of the enterprise portfolio today, and where the trouble sits.

SCA projects health score

Budget-weighted across eight dimensions: schedule, cost, risk, scope, quality, resources, stakeholders and benefits.

since January

from ⁦89⁩ to ⁦66⁩

Progress

⁦52%⁩

Planned ⁦57%⁩

SPI

0.85

CPI 0.93

Projects by status

  • On track18
  • At risk10
  • Off track4
  • Critical2
  • On hold2

Portfolio health

Pick a portfolio to drill into its programmes and projects.

Major projects

The six largest projects by budget — ⁦66%⁩ of the whole portfolio.

02Why are we late?

Lateness is not one number — these are its root causes, ranked by days of delay.

Root causes of delay

Forecast delay of active projects, in days, grouped by primary cause.

  • Unapproved variations piling up into financial claims and extension requests.

Schedule and cost performance trend

Budget-weighted, January – October 2026

  • SPI
  • CPI

AI insight

⁦74%⁩ chance Muqawil Platform — Release ⁦4⁩ slips within ⁦45⁩ days

The project is At risk today, but the SPI trend, the task-closure rate and the open risks point to a further slip.

Confidence⁦82%⁩

03What have we spent, what will it cost?

Spend to date, what is committed, and the forecast cost to completion.

Approved budget
SAR 5.2B
Spent
SAR 2.4B

⁦47%⁩ of budget

Committed
SAR 3.9B

⁦75%⁩

Estimate at completion
SAR 5.6B
Variance at completion
SAR 407.7M

⁦7.9%⁩ over budget

Actual spendCommittedApproved budgetEstimate at completion

Where does the overrun come from?

EAC minus budget for each portfolio (red is overrun) · SAR M

Monthly spend, 2026

Planned against actual, with the forecast to December · SAR M

  • Planned
  • Actual
  • Forecast

04What needs me?

Decisions waiting for your signature, and the risks that could change the picture.

Decisions waiting for the Secretary-General

By decision date. You can remind the decision owner.

Approval26 hours overdueAction time limit exceeded

Approve the October Steering Committee minutes

The minutes hold 7 decisions and 12 actions; follow-up cannot start before approval.

Decision22 hours leftAction time limit about to lapse

Pay subcontractors directly on the Al-Khobar branch rehabilitation & extension

Three subcontractors stopped work 19 days ago over unpaid dues from the main contractor; the new training and test hall wing is idle.

Decision2 days leftWithin the time limit

Refer the SCA Academy campus contractor’s claims to arbitration

SAR 96M of claims over unapproved variations; the dispute board reached no settlement.

Approval4 days leftWithin the time limit

Approve the updated corrective plan for Muqawil Release 4

The plan recovers 30 of the 42 days by adding an integration squad for four months and resequencing wave 2.

Muqawil Platform — Release 4SAR 980KRecovers ⁦30⁩ days
Budget6 days leftWithin the time limit

Release SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handover

Zones 3 and 4 of the HQ site wait on the northern plot handover and utility diversions; every month of delay costs SAR 6.8M.

SCA Headquarters, RiyadhSAR 22MRecovers ⁦45⁩ days

What you did today

No actions yet. What you approve or defer here shows in this log and on the command centre.

05Are we meeting the SCA strategy’s objectives?

Are the projects moving the targets? Strategic objectives and benefits realised.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close