The objective’s weakest KPI, “Training and test halls fitted out this year (cumulative)”, is at 81% of its target, and its heaviest project, “SCA Headquarters, Riyadh”, is Off track. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the handover of the HQ site’s northern plot with the municipality and the utility owners
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010·t.alanazi@sca.saDue 2026-10-208 days overdue2026-10-20·9 Jumada I 1448 AHK-3.1.1SCA Headquarters, Riyadh
Overdue
Take the conference & exhibition building fit-out out of the HQ construction contract and tender it separately
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020·a.asiri@sca.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHK-3.1.1SCA Headquarters, Riyadh
In progress
An extra night shift on the Qassim vocational centre until year end
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036·i.alghamdi@sca.saDue 2026-12-31In 64 days2026-12-31·22 Rajab 1448 AHK-3.1.2Qassim Vocational Qualification Centre
In progress
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
The late handover of the HQ site’s northern plot and the utility diversions held up zones 3 and 4 by about four months.
Eng. Ahmed Y. Asiri · 2026-10-12
Challenge
Steel and concrete prices and longer piles have pushed up the forecast cost of the Qassim vocational centre.
Eng. Ibrahim A. Al-Ghamdi · 2026-09-28
Note
The Project Steering Committee advised taking the conference & exhibition building fit-out out of the HQ construction contract to speed delivery.