AI insight
81% chance of a further slip within 60 days
From the SPI trend (0.80), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
69
Needs watching
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.80), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 44% done against 55% planned.
SPI 0.80, CPI 0.95.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-3.1.2HQ & major qualification centres
The project’s share of the initiative’s project budget (3 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
44%Awaiting acceptance 12%
Not handed in 44%
6 deliverables accepted
1 deliverable under inspection or acceptance
Corrective planCP-2026-04
Approved — under way
Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed
Actions
1 of 5 done
Next: Redesign the foundations through a change request · Eng. Ahmed Y. Asiri · 2026-11-04
Days won back
0 of 33
With the plan: 2027-08-03
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 92% of budget
0 approvals and 1 open action on this project
From «My actions» for this project
1 open
Cost and schedule impact
2 open risks, exposure SAR 35.4M
Impact
6 of 12 approved
2 members