Qassim Vocational Qualification Centre Subtask Last item under this branch 2027-08-01 44% Qassim Vocational Qualification Centre Planned: 2024-06-02 → 2027-05-31 Forecast: 2024-06-02 → 2027-08-01 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-05-14 100% Management & governance Planned: 2024-06-02 → 2025-01-14 Actual: 2024-06-02 → 2025-05-14
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-01-01 100% Project plan & baseline Planned: 2024-06-02 → 2024-10-19 Actual: 2024-06-02 → 2025-01-01
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-14 100% Monitoring & reporting Planned: 2024-08-28 → 2025-01-14 Actual: 2024-10-13 → 2025-05-14
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-14 100% Project plan approved Planned: 2025-01-14 → 2025-01-14 Actual: 2025-05-14 → 2025-05-14 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-02-03 100% Design & permits Planned: 2024-11-22 → 2025-07-06 Actual: 2025-02-23 → 2026-02-03
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-24 100% Detailed design Planned: 2024-11-22 → 2025-04-10 Actual: 2025-02-23 → 2025-09-24
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-03 100% Permits & approvals Planned: 2025-02-17 → 2025-07-06 Actual: 2025-07-06 → 2026-02-03
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-03 100% Designs approved Planned: 2025-07-06 → 2025-07-06 Actual: 2026-02-03 → 2026-02-03 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-09 68% Civil works Planned: 2025-05-15 → 2026-03-23 Forecast: 2025-11-04 → 2027-03-09 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-16 100% Site works & excavation Planned: 2025-05-15 → 2025-10-01 Actual: 2025-11-16 → 2026-06-16
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-27 100% Structure Planned: 2025-08-10 → 2025-12-27 Actual: 2026-03-29 → 2026-10-27
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-09 5% Finishes Planned: 2025-11-04 → 2026-03-23 Forecast: 2025-11-04 → 2027-03-09 Float: 0d Drag to change its duration +351
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-09 0% Build complete Planned: 2026-03-23 → 2026-03-23 Forecast: 2027-03-09 → 2027-03-09 Float: 145d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-06-04 0% MEP works Planned: 2026-01-30 → 2026-12-09 Forecast: 2027-02-19 → 2027-06-04 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-07 0% Supply Planned: 2026-01-30 → 2026-06-18 Forecast: 2027-02-19 → 2027-04-07 Float: 0d Drag to change its dates +293
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-06 0% Installation Planned: 2026-04-27 → 2026-09-13 Forecast: 2027-03-20 → 2027-05-06 Float: 0d Drag to change its dates +235
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-04 0% Testing & commissioning Planned: 2026-07-23 → 2026-12-09 Forecast: 2027-04-18 → 2027-06-04 Float: 0d Drag to change its dates +177
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-04 0% Testing & acceptance complete Planned: 2026-12-09 → 2026-12-09 Forecast: 2027-06-04 → 2027-06-04 Float: 58d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-08-01 0% Handover Planned: 2026-10-17 → 2027-05-31 Forecast: 2027-05-17 → 2027-08-01 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-07-03 0% Provisional acceptance Planned: 2026-10-17 → 2027-03-05 Forecast: 2027-05-17 → 2027-07-03 Float: 0d Drag to change its dates +120
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-01 0% Final acceptance Planned: 2027-01-12 → 2027-05-31 Forecast: 2027-06-15 → 2027-08-01 Float: 0d Drag to change its dates +62
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-01 0% Final handover Planned: 2027-05-31 → 2027-05-31 Forecast: 2027-08-01 → 2027-08-01 Float: 0d Drag to change its dates Final handover