PMO Command Centre
The enterprise view of the portfolio: status, performance, early warning, escalations, decisions and data quality.
- Total projects
- 36
- Weighted progress
- 52%−5%
- SPI
- 0.85−0.04
- CPI
- 0.93−0.02
- Open high risks
- 18
SAR 5.2B
Planned 57%
Schedule performance (SPI)
Cost performance (CPI)
of 45 open risks
Pick a status to filter the map and lists
Portfolio performance
The six portfolios by health score, forecast cost and the two performance indices, with the project map by risk and value.
Portfolio map: risk × strategic value
Bubble size = budget. Pick a project to drill down.
- On track
- At risk
- Off track
- Critical
- On hold
Portfolio board
Pick a portfolio to drill into its programmes and projects.
| Portfolio | Health score | Estimate at completion | SPI | CPI | Status mix |
|---|---|---|---|---|---|
| 7 projects | SAR 183.9M | 0.92Schedule performance index · 0.92 | 0.98Cost performance index · 0.98 | ||
| 4 projects | SAR 1.5B | 0.79Schedule performance index · 0.79 | 0.88Cost performance index · 0.88 | ||
| 7 projects | SAR 376M | 0.91Schedule performance index · 0.91 | 0.94Cost performance index · 0.94 | ||
| 5 projects | SAR 726M | 0.83Schedule performance index · 0.83 | 0.90Cost performance index · 0.90 | ||
| 8 projects | SAR 2.8B | 0.87Schedule performance index · 0.87 | 0.95Cost performance index · 0.95 | ||
| 5 projects | SAR 30.5M | 0.98Schedule performance index · 0.98 | 1.00Cost performance index · 1.00 |
Early warning and escalations
The early-warning engine reads the SPI trend, the task-closure rate and the open risks; whatever breaks a threshold reaches the escalation queue.
Slip forecasts
16 projects with a 35%+ chance of slipping
- 97%
Critical today, but a 97% chance of slipping within 30 days.
CriticalSPI0.70Schedule performance index · 0.70Schedule variance: 30.5% - 95%
Critical today, but a 95% chance of slipping within 30 days.
CriticalSPI0.74Schedule performance index · 0.74Schedule variance: 26.1% - 88%
Off track today, but a 88% chance of slipping within 60 days.
Off trackSPI0.82Schedule performance index · 0.82Schedule variance: 17.6% - 86%
Off track today, but a 86% chance of slipping within 30 days.
Off trackSPI0.82Schedule performance index · 0.82Schedule variance: 17.6% - 84%
Off track today, but a 84% chance of slipping within 45 days.
Off trackSPI0.78Schedule performance index · 0.78Schedule variance: 22.0% - 81%
Off track today, but a 81% chance of slipping within 60 days.
Off trackSPI0.80Schedule performance index · 0.80Schedule variance: 20.0% - 74%
At risk today, but a 74% chance of slipping within 45 days.
At riskSPI0.87Schedule performance index · 0.87Schedule variance: 13.4%
Escalation queue
What crossed a variance threshold or an action time limit, and who is handling it.
- ESC-2026-031Schedule varianceExecutive CommitteeBeing handled
Schedule variance 31%; forecast 152 days past baseline
Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa2026-10-0524 Rabiʻ II 1448 AH40 hours overdueAction time limit exceeded - ESC-2026-032Critical riskExecutive CommitteeOpen
Critical risk (25): main-contractor cash distress, subcontractors idle
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa2026-10-198 Jumada I 1448 AH22 hours leftAction time limit about to lapse - ESC-2026-033Schedule variancePMOOpen
Schedule variance 18% from the late land handover in zones 3 and 4
Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.sa2026-10-2110 Jumada I 1448 AH30 hours leftAction time limit about to lapse - ESC-2026-034Action time limit passedPMOBeing handled
The integration-engineer impediment is three days past its action time limit
Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa2026-10-2211 Jumada I 1448 AH18 hours leftAction time limit about to lapse - ESC-2026-035Cost overrunPMOOpen
The ground-improvement variation pushes EAC SAR 22.5M past contingency
Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.sa2026-10-2413 Jumada I 1448 AH3 days leftWithin the time limit - ESC-2026-036Critical riskPMOOpen
Unforeseen ground needs the foundations of five axes redesigned
Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.sa2026-10-2615 Jumada I 1448 AH4 days leftWithin the time limit
Budget, forecast and risk
The forecast-cost trend with a confidence band to year end, and the map of open risks.
Estimate at completion
Actual to October, then forecast with a confidence band · axis in SAR billions · Estimate at completion
- EAC
- Approved budget
- Forecast
- Forecast range
Open-risk map
45 risks · pick a cell to list its risks
- Critical6
- High12
- Medium24
- Low3
- Risks 45
Impact
Highest-scoring risks
- 16Nafath and Government Service Bus integration interfaces not ready on timeSAR 2.4M
- 16Shortage of integration and back-end engineers on the vendor teamSAR 1.9M
- 16Customisation and Etimad integration costs exceeding the approved contingencySAR 6.8M
- 20Steel and concrete price rises driving price-adjustment claimsSAR 48M
- 20Late handover of the northern plot and utility diversions in zones 3 and 4SAR 31M
Strategic alignment and benefits
How much of the budget serves the SCA strategy’s objectives, and how much benefit has actually landed.
Budget by objective and portfolio
A project linked to two objectives counts in both · Budget (SAR M)
Average alignment score
83
out of 100
Strongly aligned budget
77%
Projects scoring 80+ on alignment
Objectives served
12 / 12
of the SCA strategy’s objectives
Benefits realised by portfolio
Planned to date against realised · SAR M
- Planned to date
- Realised
Decisions needed
What waits for a committee or the Secretary-General, by action time limit.
Waiting for a decision
15 decisions
- 6 days overdueAction time limit exceededAcademy campus 150-day extension
Change request · SCA Academy Campus, Riyadh
- 26 hours overdueAction time limit exceeded
- 18 hours leftAction time limit about to lapseRule on the escalated impediment — integration engineers withdrawn
Decision · Muqawil Platform — Release 4
- 20 hours leftAction time limit about to lapseAdd membership transfer & record merge
Change request · Muqawil Platform — Release 4
- 22 hours leftAction time limit about to lapseDirect payment to subcontractors at the Al-Khobar branch
Decision · Al-Khobar Branch — Rehabilitation & Extension
- 44 hours leftAction time limit about to lapseSCA ERP customisation budget increase
Budget · SCA ERP System
- 2 days leftAction time limit about to lapseDecide on taking the Academy campus claims to the dispute board
Decision · SCA Academy Campus, Riyadh
- 4 days leftWithin the time limitApprove the updated corrective plan for Muqawil
Approval · Muqawil Platform — Release 4
- 4 days leftWithin the time limitApprove the change request for extra Muqawil integration capacity
Change request · Muqawil Platform — Release 4
- 5 days leftWithin the time limit
- 6 days leftWithin the time limitReview the SCA ERP re-baseline
Gate review · SCA ERP System
- 7 days leftWithin the time limitPreliminary handover readiness — Khamis Mushait training centre
Gate review · Khamis Mushait Training Centre Rehabilitation
- 7 days leftWithin the time limitAccept a deliverable: the wave 1 service package (24 services)
Approval · Muqawil Platform — Release 4
- 13 days leftWithin the time limitApprove the Project Tracking Platform charter before the initiation gate
Gate review · Project Tracking Platform — National Phase
- 28 days leftWithin the time limitVerify the conditions on the Project Tracking Platform gate
Gate review · Project Tracking Platform — National Phase
The Secretary-General’s list
Decisions raised to the Secretary-General and the Executive Committee, and where they stand now.
- Pay subcontractors directly on the Al-Khobar branch rehabilitation & extensionAwaiting decision
- Refer the SCA Academy campus contractor’s claims to arbitrationAwaiting decision
- Approve the updated corrective plan for Muqawil Release 4Awaiting decision
- Release SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handoverAwaiting decision
- Approve the October Steering Committee minutesAwaiting decision
Compliance and data quality
A composite score per project manager: data quality 45%, mandatory documents complete 35%, update freshness 20%.
Leaders
The five most compliant project managers
- 1Abeer H. Al-ShamraniHead of Strategy ManagementAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa95Data quality94%Documents96%Freshness97%
1 project
- 2Tariq S. Al-YamiHead, Performance & RiskTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa93Data quality97%Documents99%Freshness78%
2 projects
- 3Eng. Ahmed Y. AsiriDirector, Construction ProjectsEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa90Data quality90%Documents89%Freshness91%
2 projects
- 4Eng. Yasser M. Al-ZahraniDirector, CybersecurityEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa90Data quality92%Documents93%Freshness84%
2 projects
- 5Karim HaddadSenior Digital Delivery Consultant — PMOKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa90Data quality93%Documents95%Freshness74%
3 projects
Laggards
They need support from the PMO
- 1Rami Al-KhatibConferences & Partnerships ConsultantRami Al-KhatibConferences & Partnerships ConsultantP-045r.alkhatib@sca.sa66Data quality70%Documents71%Freshness49%
1 project
- 2Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilityGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa68Data quality78%Documents79%Freshness31%
2 projects
- 3Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa69Data quality75%Documents78%Freshness43%
2 projects
- 4Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa70Data quality76%Documents72%Freshness54%
2 projects
- 5Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa72Data quality75%Documents75%Freshness58%
3 projects
Late updates
4 active projects not updated for more than 14 days
Arar Vocational Qualification Centre
Last update 56 days ago · Data quality 58%
Smart Test-hall Proctoring & Access Control
Last update 44 days ago · Data quality 54%
Secure Enterprise Network
Last update 37 days ago · Data quality 61%
Irtiqaa Portal — Release 2
Last update 34 days ago · Data quality 66%