PRJ-2026-007 · From item 2
SCA Academy Campus, RiyadhPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SAR 640M
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Academy campus contractor claims; Digital Services & Platforms portfolio progress.
Held on
13 October 202610:00 – 12:05
105 of 120 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
SCA Academy campus — contractor claims
DecisionEng. Shahad M. Al-Malki
50 min
Digital Services & Platforms portfolio progress
DiscussionFaisal A. Al-Shehri
40 min
Any other business
DiscussionDr. Abdullah S. Al-Qahtani
10 min
1. Approve the previous minutes
September minutes approved.
2. SCA Academy campus — contractor claims
PRJ-2026-007Claims total SAR 74M and 150 days. Referred to the contract’s dispute board; Academy Facilities prepares the file.
3. Digital Services & Platforms portfolio progress
PF-DTThe committee wants a portfolio brief in November focused on the risk in integrating with government agencies.
4. Any other business
No minutes were written for this item.
Voting rule: Two-thirds of those present for baseline decisions, simple majority otherwise
Academy campus contractor claims referred to dispute resolution
DEC-2026-037Approved
For 6Against 0Abstain 0Carried
They show in the task register and on the owner’s calendar
ACT-0323Faisal A. Al-Shehri
Quorum: Five of seven voting members, including the chair or vice-chair
At least 5 voting members needed
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007 · From item 2
SCA Academy Campus, RiyadhPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Agenda item needing a decision · PRJ-2026-007
SCA Academy campus — contractor claimsFrom item 2
Change request awaiting decision · CR-2026-005
Variation 7: revise the central HVAC systemSCA Academy Campus, Riyadh
Change request awaiting decision · CR-2026-006
Extend the contract by 150 daysSCA Academy Campus, Riyadh
Corrective plan awaiting approval · CP-2026-03
SCA Academy Campus, RiyadhISS-0109 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
CP-2026-03 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade on the consultant’s advice
ACT-0311 · Eng. Ibrahim A. Al-Ghamdi