The central decision log with reasons, impact and affected projects.
across 5 committees
since 2026-09-28
conditions being tracked
in the next two weeks
their tasks or follow-up are past due
this year
Every decision: what was decided, when, by whom, in which committee, why, its impact, its documents and the projects it affects.
Every escalation with its rung, its reason and the support asked: the kind, the amount, from whom, and the decision that answered it.
ESC-2026-021Awaiting decisionExecutive committee
ISS-0113Site labour stopped for 4 days over late wagesAl-Khobar Branch — Rehabilitation & Extension
Labour at the Al-Khobar site stopped for four days over late wages; risk RSK-0021 is at 25 of 25
Raised 2026-10-28To: Executive CommitteeIn 2 days2026-10-3019 Jumada I 1448 AH
FundingSAR 6.4M· Asked from: Executive Committee
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ESC-2026-019Awaiting decisionExecutive committee
ISS-0109Façade works stopped — samples not approvedSCA Academy Campus, Riyadh
Façade works at the Academy campus stopped over unapproved samples; the critical path slips every day
Raised 2026-10-27To: Executive CommitteeIn 5 days2026-11-0222 Jumada I 1448 AH
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
ESC-2026-018Being acted onProgramme manager
ISS-0103Two vendor integration engineers withdrawn with no replacementMuqawil Platform — Release 4
Two vendor integration engineers withdrawn; team velocity halved
Raised 2026-10-25To: Change CommitteeIn 12 days2026-11-0929 Jumada I 1448 AH
PeopleSAR 980K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ESC-2026-016Being acted onPMO director
ISS-0101Shared Nafath test environment down for 9 daysMuqawil Platform — Release 4
The shared Nafath test environment has been down for nine days and integration testing is fully blocked
Raised 2026-10-26To: Dr. Noura M. Al-OtaibiIn 7 days2026-11-0424 Jumada I 1448 AH
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
ESC-2026-015Awaiting decisionPMO director
ISS-0116Excavation clashing with a high-voltage line in zone 4SCA Headquarters, Riyadh
Excavation in zone 4 of the headquarters site clashes with an undocumented high-voltage line
Raised 2026-10-25To: Dr. Noura M. Al-OtaibiIn 11 days2026-11-0828 Jumada I 1448 AH
Coordination· Asked from: Eng. Bandar M. Al-Shammari
Urgent coordination with the Saudi Electricity Company to divert the line within 30 days
ESC-2026-014Awaiting decisionPMO director
ISS-0121Foundation works stopped pending building permitsJeddah Branch & Qualification Centre
Foundation works at the Jeddah branch stopped waiting for the municipality’s building permits
Raised 2026-10-26To: Dr. Noura M. Al-OtaibiIn 8 days2026-11-0525 Jumada I 1448 AH
An approval· Asked from: Eng. Turki A. Al-Anazi
A sector-head letter to the Jeddah municipality to speed up the permits