Corrective plans for serious delay: actions, owners, dates, approval and follow-up, and the projects that need one.
this year, in your scope
followed weekly
or sent back
projects without a plan the rule asks for
past their dates
across the plans
When a corrective plan is required
An active project needs a corrective plan when its forecast finish is more than 40 days past the baseline, or its schedule performance index (SPI) falls below 0.85.
Slip past the baseline
> 40
Schedule performance index
< 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
The rule applies and no plan has been prepared yet.
Corrective plan requiredOff track
Jeddah Branch & Qualification Centre95 days lateSPI 0.78Eng. Fahad T. Al-Sulami
Corrective plan requiredAt risk
Smart Test-hall Proctoring & Access Control45 days lateSPI 0.88Eng. Waleed O. Al-Juhani
Corrective plan requiredAt risk
Correspondence & Document Management System (DMS)46 days lateSPI 0.95Dana S. Al-Saleh
The plan, its status, what triggered it, its actions, the days won back and its approval.
Display options
| Owner | Next step | ||||||
|---|---|---|---|---|---|---|---|
CP-2026-01 · Version 2 Muqawil Platform — Release 4 | Awaiting approval | 48 days lateSPI 0.85 | 1 of 6 doneOverdue: 1 | 6 of 21 | 2027-05-12 | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa | Programme manager · Eng. Reem K. Al-Dosari |
CP-2026-02 · Version 1 Al-Khobar Branch — Rehabilitation & Extension | Approved — under way | 104 days lateSPI 0.76 | 1 of 5 doneOverdue: 1 | 0 of 45 | 2027-02-03 | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa | — |
CP-2026-03 · Version 1 SCA Academy Campus, Riyadh | Awaiting approval | 131 days lateSPI 0.72 | 0 of 4 doneOverdue: 1 | 0 of 60 | 2027-06-01 | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Project Management Office · Dr. Noura M. Al-Otaibi |
CP-2026-04 · Version 1 Qassim Vocational Qualification Centre | Approved — under way | 55 days lateSPI 0.83 | 1 of 5 done | 0 of 33 | 2027-08-03 | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | — |
CP-2026-05 · Version 1 SCA ERP System | Sent back | 52 days lateSPI 0.83 | 1 of 4 done | 10 of 32 | 2027-02-27 | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Project Approval Committee · Dr. Noura M. Al-Otaibi |