PRJ-2026-013At risk4ExecutionConstruction

Smart Test-hall Proctoring & Access Control

Add to watchlist

4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 74M

Actual cost

SAR 62.2M

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 78.7M

SAR +4.7M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−6

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦58%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.88⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦79%⁩ done against ⁦90%⁩ planned.

SPI ⁦0.88⁩, CPI ⁦0.94⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.2Efficient, sustainable SCA facilities

Main initiative

SI-3.3.1Smart centres

Contribution to the initiative⁦20%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
Added outside the annual work plan
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦79%⁩

Awaiting acceptance ⁦9%⁩

Not handed in ⁦12%⁩

9 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Supply⁦11%⁩
  • Installation⁦11%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩

1 deliverable under inspection or acceptance

  • Testing & commissioning⁦9%⁩

Corrective plan requiredThe project is seriously late (45 days late) and has no corrective plan yet.

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦93%⁩ of budget

62.2M/ 74M4.7Mprojected overrun(⁦6.4%⁩)
Actual spend
62.2M
Committed
68.8M
Approved budget
74M
Estimate at completion
78.7M

Next milestones

  • Closure⁦2026-12-15⁩was ⁦2026-10-31⁩Late

Waiting on someone

⁦1⁩ approval and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

Actions

⁦1⁩ open

  • Update progress and the plan in MunjazEng. Waleed O. Al-Juhani7 days overdue2026-10-2110 Jumada I 1448 AHMedium

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

2 open risks, exposure SAR 3.2M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0030Camera and gate quantity variances between drawings and site1Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0031Late integration of the central monitoring room with building systemsProbability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium2
  • Low0

Deliverables

⁦9⁩ of ⁦12⁩ approved

  • Project plan & baseline013-D1 · V1 · CRT-013-01⁦3%⁩Eng. Waleed O. Al-Juhani⁦2025-05-06⁩2025-05-068 Dhuʻl-Qiʻdah 1446 AHApproved
  • Monitoring & reporting013-D2 · V1 · CRT-013-02⁦3%⁩Eng. Bandar M. Al-Shammari⁦2025-06-24⁩2025-06-2428 Dhuʻl-Hijjah 1446 AHApproved
  • Detailed design013-D3 · V1 · CRT-013-03⁦6%⁩Eng. Bandar M. Al-Shammari⁦2025-08-13⁩2025-08-1319 Safar 1447 AHApproved
  • Permits & approvals013-D4 · V1 · CRT-013-04⁦6%⁩Eng. Turki A. Al-Anazi⁦2025-10-01⁩2025-10-019 Rabiʻ II 1447 AHApproved
  • Site works & excavation013-D5 · V1 · CRT-013-05⁦13%⁩Eng. Turki A. Al-Anazi⁦2025-11-19⁩2025-11-1928 Jumada I 1447 AHApproved
  • Structure013-D6 · V1 · CRT-013-06⁦13%⁩Eng. Waleed O. Al-Juhani⁦2026-01-08⁩2026-01-0819 Rajab 1447 AHApproved
  • Finishes013-D7 · V1 · CRT-013-07⁦13%⁩Eng. Bandar M. Al-Shammari⁦2026-02-26⁩2026-02-269 Ramadan 1447 AHApproved
  • Supply013-D8 · V1 · CRT-013-08⁦11%⁩Eng. Waleed O. Al-Juhani⁦2026-04-17⁩2026-04-1729 Shawwal 1447 AHApproved
  • Installation013-D9 · V1 · CRT-013-09⁦11%⁩Eng. Bandar M. Al-Shammari⁦2026-06-05⁩2026-06-0519 Dhuʻl-Hijjah 1447 AHApproved
  • Testing & commissioning013-D10 · V1⁦9%⁩Eng. Turki A. Al-Anazi96 days overdue2026-07-2410 Safar 1448 AHSubmitted
  • Provisional acceptance013-D11 · V0⁦6%⁩Eng. Bandar M. Al-Shammari46 days overdue2026-09-121 Rabiʻ II 1448 AHDraft
  • Final acceptance013-D12 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 3 days2026-10-3120 Jumada I 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Waleed O. Al-Juhani · Director, Facilities Operations & MaintenanceEng. Bandar M. Al-Shammari · Director General, Facilities & Premises
  • Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceProject managerP-021w.aljuhani@sca.sa⁦30%⁩
  • Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesProject sponsorP-013b.alshammari@sca.sa⁦15%⁩

Documents

  • No documents yet