Smart Test-hall Proctoring & Access Control
Add to watchlist4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started