5 projects in this portfolio are pulling its health down
Most of it comes from “Qassim Vocational Qualification Centre” (SPI 0.80) and “SCA Headquarters, Riyadh” (SPI 0.82). Fixing those two lifts the portfolio towards 67 within two quarters.
Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.
· Proposed and cancelled projects never count.
· Left out of this portfolio now: 1
· For comparison: weighting by budget alone gives 32.8%
8Unified Operations Centre for Centres & PlatformsPRJ-2026-024·Priority score 64On track
Portfolio priorities 2026–2027
Unblock the Buraydah site on the HQ’s critical pathLand handover is five months late, and the HQ’s standard training-hall layout waits on its Qassim trial.
Fit out 120 training & test halls this year97 commissioned to October.
Offer the HQ car parks and service space to private partnersMoves revenue from alternative sources toward target.
Objectives & KPIs
Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.