RSK-0033Secure Enterprise Network

Municipal objections to trenching in built-up districts

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Weak engagement of the owning departments, branches and contractors, and diverging expectations

Preventive controls

  • An updated engagement and communication plan
  • Regular meetings with the parties concerned

2 / 2

Event

Municipal objections to trenching in built-up districts

12MediumTrigger

A formal objection from a stakeholder

Contingency

Take it to the steering committee

Impact

Objections, late approvals and low adoption

SAR 2.2M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 2.2M

Residual

⁦67⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 37 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Omar H. Bawazir

    Currently followed up here
  2. 2

    Programme manager

    Eng. Omar H. Bawazir

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • An updated engagement and communication plan

    Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
    In progressIn 33 days2026-11-3020 Jumada II 1448 AH
  • Regular meetings with the parties concerned

    Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
    Not startedIn 33 days2026-11-3020 Jumada II 1448 AH

Trigger

A formal objection from a stakeholder

Contingency

Take it to the steering committee