Secure Enterprise Network
Add to watchlistFibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started