Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • No documents

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 018-D1Project plan & baselinePRJ-2026-018_1.1_v1.pdfApprovedDeliverable
  • 018-D2Monitoring & reportingPRJ-2026-018_1.2_v1.pdfApprovedDeliverable
  • 018-D3Detailed designPRJ-2026-018_2.1_v1.pdfApprovedDeliverable
  • 018-D4Permits & approvalsPRJ-2026-018_2.2_v1.pdfApprovedDeliverable
  • 018-D5Site works & excavationPRJ-2026-018_3.1_v1.pdfApprovedDeliverable
  • 018-D6StructurePRJ-2026-018_3.2_v1.pdfApprovedDeliverable
  • 018-D7FinishesPRJ-2026-018_3.3_v1.pdfIn reviewDeliverable
  • 018-D8SupplyNo evidence filed yetDraftDeliverable
  • 018-D9InstallationNo evidence filed yetDraftDeliverable
  • 018-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 018-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 018-D12Final acceptanceNo evidence filed yetDraftDeliverable
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close