Secure Enterprise Network
Add to watchlistFibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate12 March 2025All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionGoDate11 May 2025All criteria and required documents met.InitiationComplete
- Gate into «Execution»DecisionGoDate20 August 2025All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate12 December 2026ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 2 required documents not approved
Checklist
5 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
2 of 4 approved
- Deliverable completion certificatesSubmitted — awaiting acceptance · V1
- Project closure & handover formSubmitted — awaiting acceptance · V1
- Lessons-learned logApproved · V1
- Benefits measurement planApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Met
Awaiting evidence from the project team.
Quality & securityweight 25%Met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Nayef H. Al-BuqamiProject ownerVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending