Secure Enterprise Network Subtask Last item under this branch 2027-03-01 55% Secure Enterprise Network Planned: 2025-05-11 → 2027-01-31 Forecast: 2025-05-11 → 2027-03-01 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-12-08 100% Management & governance Planned: 2025-05-11 → 2025-09-18 Actual: 2025-05-11 → 2025-12-08
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-18 100% Project plan & baseline Planned: 2025-05-11 → 2025-07-30 Actual: 2025-05-11 → 2025-09-18
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-08 100% Monitoring & reporting Planned: 2025-06-30 → 2025-09-18 Actual: 2025-07-31 → 2025-12-08
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-08 100% Project plan approved Planned: 2025-09-18 → 2025-09-18 Actual: 2025-12-08 → 2025-12-08 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-05-19 100% Design & permits Planned: 2025-08-19 → 2025-12-27 Actual: 2025-10-20 → 2026-05-19
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-27 100% Detailed design Planned: 2025-08-19 → 2025-11-07 Actual: 2025-10-20 → 2026-02-27
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-19 100% Permits & approvals Planned: 2025-10-08 → 2025-12-27 Actual: 2026-01-09 → 2026-05-19
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-19 100% Designs approved Planned: 2025-12-27 → 2025-12-27 Actual: 2026-05-19 → 2026-05-19 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-11 97% Civil works Planned: 2025-11-27 → 2026-05-26 Forecast: 2026-03-07 → 2026-11-11 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-08 100% Site works & excavation Planned: 2025-11-27 → 2026-02-15 Actual: 2026-03-31 → 2026-08-08
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Structure Planned: 2026-01-16 → 2026-04-06 Actual: 2026-06-20 → 2026-10-26
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 92% Finishes Planned: 2026-03-07 → 2026-05-26 Forecast: 2026-03-07 → 2026-11-11 Float: 0d Drag to change its duration +169
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 0% Build complete Planned: 2026-05-26 → 2026-05-26 Forecast: 2026-11-11 → 2026-11-11 Float: 110d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-16 0% MEP works Planned: 2026-04-26 → 2026-10-23 Forecast: 2026-10-28 → 2027-01-16 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-03 0% Supply Planned: 2026-04-26 → 2026-07-15 Forecast: 2026-10-28 → 2026-12-03 Float: 0d Drag to change its dates +141
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-25 0% Installation Planned: 2026-06-15 → 2026-09-03 Forecast: 2026-11-19 → 2026-12-25 Float: 0d Drag to change its dates +113
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-16 0% Testing & commissioning Planned: 2026-08-04 → 2026-10-23 Forecast: 2026-12-11 → 2027-01-16 Float: 0d Drag to change its dates +85
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-16 0% Testing & acceptance complete Planned: 2026-10-23 → 2026-10-23 Forecast: 2027-01-16 → 2027-01-16 Float: 44d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-01 0% Handover Planned: 2026-09-23 → 2027-01-31 Forecast: 2027-01-02 → 2027-03-01 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-07 0% Provisional acceptance Planned: 2026-09-23 → 2026-12-12 Forecast: 2027-01-02 → 2027-02-07 Float: 0d Drag to change its dates +57
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-01 0% Final acceptance Planned: 2026-11-12 → 2027-01-31 Forecast: 2027-01-24 → 2027-03-01 Float: 0d Drag to change its dates +29
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-01 0% Final handover Planned: 2027-01-31 → 2027-01-31 Forecast: 2027-03-01 → 2027-03-01 Float: 0d Drag to change its dates Final handover