Projects

The project register by code, name, sector, classification, status, stage, year and owner.

Working on:Saudi Contractors Authority
Projects in scope
36

30 active

Approved budget
SAR 5.2B

Forecast at completion SAR 5.6B

Off track or critical
6

plus ⁦10⁩ at risk

On the watchlist
7

Followed closely by leadership

Try:
⁦36⁩ results
Export CSV
Add to watchlist
Energy Retrofit of Existing SCA Buildings (ESCO)
Building Rehabilitation & Sustainability Portfolio
PRJ-2026-026SuspendedOperationalSupport2026WP-2026-026On hold3Planning⁦8%⁩33M33M0.89Schedule performance index · 0.891.00Cost performance index · 1.00⁦2027-10-31⁩123 days late1Data quality · GoodEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa
Add to watchlist
Wadi Al-Dawasir Vocational Qualification Centre
Academy & Qualification Centres Portfolio
PRJ-2026-033SuspendedStrategicQualification2026WP-2026-033On hold3Planning⁦2%⁩210M210M1.00Schedule performance index · 1.001.00Cost performance index · 1.00⁦2028-12-31⁩184 days late1Data quality · ExcellentEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa
Remove from watchlist
Al-Khobar Branch — Rehabilitation & Extension
Building Rehabilitation & Sustainability Portfolio
PRJ-2026-004ActiveOperationalSupport2024WP-2024-004Critical4Execution⁦68%⁩412M490.5M−78.5M0.74Schedule performance index · 0.740.84Cost performance index · 0.84⁦2027-02-03⁩126 days late3Data quality · GoodEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa
Remove from watchlist
SCA Academy Campus, Riyadh
Academy & Qualification Centres Portfolio
PRJ-2026-007ActiveStrategicQualification2024WP-2024-007Critical4Execution⁦57%⁩640M780.5M−140.5M0.70Schedule performance index · 0.700.82Cost performance index · 0.82⁦2027-06-01⁩152 days late3Data quality · GoodEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa
Remove from watchlist
SCA ERP System
Technology & Enterprise Systems Portfolio
PRJ-2026-001ActiveOperationalDigital2025WP-2025-001Off track4Execution⁦61%⁩64.5M73.3M−8.8M0.82Schedule performance index · 0.820.88Cost performance index · 0.88⁦2027-02-27⁩58 days late3Data quality · ExcellentDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa
Remove from watchlist
SCA Headquarters, Riyadh
Headquarters & Regional Centres PortfolioCorrective plan required
PRJ-2026-002ActiveStrategicSupport2024WP-2024-002Off track4Execution⁦42%⁩1.2B1.3B−88.8M0.82Schedule performance index · 0.820.93Cost performance index · 0.93⁦2027-09-12⁩74 days late4Data quality · ExcellentEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
Remove from watchlist
Jeddah Branch & Qualification Centre
Academy & Qualification Centres PortfolioCorrective plan required
PRJ-2026-006ActiveStrategicQualification2024WP-2024-006Off track4Execution⁦39%⁩286M321.3M−35.3M0.78Schedule performance index · 0.780.89Cost performance index · 0.89⁦2027-07-04⁩95 days late2Data quality · ExcellentEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa
Remove from watchlist
Qassim Vocational Qualification Centre
Headquarters & Regional Centres Portfolio
PRJ-2026-020ActiveStrategicSupport2024WP-2024-020Off track4Execution⁦44%⁩345M363.2M−18.2M0.80Schedule performance index · 0.800.95Cost performance index · 0.95⁦2027-08-03⁩64 days late2Data quality · ExcellentEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
Add to watchlist
SCA Backup Data Centre
Technology & Enterprise Systems Portfolio
PRJ-2026-003ActiveOperationalDigital2025WP-2025-003At risk4Execution⁦72%⁩148M162.6M−14.6M0.90Schedule performance index · 0.900.91Cost performance index · 0.91⁦2027-01-07⁩38 days late2Data quality · ExcellentEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
Add to watchlist
SCA Systems Migration to the Cloud
Technology & Enterprise Systems Portfolio
PRJ-2026-009ActiveOperationalDigital2025WP-2025-009At risk4Execution⁦47%⁩52M53.6M−1.6M0.89Schedule performance index · 0.890.97Cost performance index · 0.97⁦2027-03-21⁩21 days late1Data quality · ExcellentEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
Total · 365.2B5.6B
⁦1⁩–⁦10⁩ of ⁦36⁩