Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-033On hold3PlanningConstruction

Wadi Al-Dawasir Vocational Qualification Centre

Add to watchlist

A permanent training and skills-test centre for the south of the Riyadh region, waiting for the land handover and title deed.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−14

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2%⁩ done against ⁦2%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.3A better contractor experience and service quality

Main initiative

Under no initiative — listed under «projects with no strategic link»

Secondary links

No secondary links

Annual work-plan line
WP-2026-033
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦2%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦98%⁩

1 deliverable accepted

  • Project plan & baseline⁦2%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦2⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    4.2M/ 210M
    Actual spend
    4.2M
    Committed
    4.6M
    Approved budget
    210M
    Estimate at completion
    210M

    Next milestones

    • 50% of works complete⁦2027-08-10⁩was ⁦2027-05-10⁩Late
    • Provisional acceptance⁦2028-09-08⁩was ⁦2028-04-23⁩Late
    • Closure⁦2028-12-31⁩was ⁦2028-06-30⁩Late

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    1 open risk, exposure SAR 12M

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0044Late land handover and title deed from the owning entity in Wadi Al-DawasirProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical1
    • High0
    • Medium0
    • Low0

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦12⁩ approved

    • Project plan & baseline033-D1 · V1 · CRT-033-01⁦2%⁩Eng. Shahad M. Al-Malki⁦2026-06-17⁩2026-06-172 Muharram 1448 AHApproved
    • Monitoring & reporting033-D2 · V0⁦3%⁩Eng. Abdulrahman S. Al-Harbi65 days overdue2026-08-2411 Rabiʻ I 1448 AHDraft
    • Detailed design033-D3 · V0⁦6%⁩Eng. Abdulrahman S. Al-HarbiIn 2 days2026-10-3019 Jumada I 1448 AHDraft
    • Permits & approvals033-D4 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 70 days2027-01-0628 Rajab 1448 AHDraft
    • Site works & excavation033-D5 · V0⁦13%⁩Eng. Turki A. Al-AnaziIn 138 days2027-03-157 Shawwal 1448 AHDraft
    • Structure033-D6 · V0⁦13%⁩Eng. Shahad M. Al-MalkiIn 205 days2027-05-2115 Dhuʻl-Hijjah 1448 AHDraft
    • Finishes033-D7 · V0⁦13%⁩Eng. Abdulrahman S. Al-HarbiIn 273 days2027-07-2824 Safar 1449 AHDraft
    • Supply033-D8 · V0⁦10%⁩Eng. Shahad M. Al-MalkiIn 341 days2027-10-044 Jumada I 1449 AHDraft
    • Installation033-D9 · V0⁦10%⁩Eng. Abdulrahman S. Al-HarbiIn 408 days2027-12-1012 Rajab 1449 AHDraft
    • Testing & commissioning033-D10 · V0⁦10%⁩Eng. Turki A. Al-AnaziIn 476 days2028-02-1620 Ramadan 1449 AHDraft
    • Provisional acceptance033-D11 · V0⁦7%⁩Eng. Abdulrahman S. Al-HarbiIn 543 days2028-04-2328 Dhuʻl-Qiʻdah 1449 AHDraft
    • Final acceptance033-D12 · V0⁦7%⁩Eng. Turki A. Al-AnaziIn 611 days2028-06-307 Safar 1450 AHDraft

    Team, contracts & documents

    Team

    1 member

    Eng. Shahad M. Al-Malki · Director, Academy Facilities
    • Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesProject manager (on hold)P-022s.almalki@sca.sa⁦10%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close