Saudi Contractors AuthorityMunjaz11My actionsNotifications

RSK-0044Wadi Al-Dawasir Vocational Qualification Centre

Late land handover and title deed from the owning entity in Wadi Al-Dawasir

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Latest escalation · ESC-2026-011

Executive committee

The Wadi Al-Dawasir centre’s title deed sits with another government body; design and tender are on hold

Coordination· Asked from: Dr. Abdullah S. Al-Qahtani

A letter from the Secretary-General to the owning body to complete the allocation

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The Wadi Al-Dawasir title deed sits with another government body and the allocation to the Authority is incomplete

Preventive controls

  • A letter from the Secretary-General to the owning body
  • Identify a fallback plot with the governorate municipality

1 / 2

Event

Late land handover and title deed from the owning entity in Wadi Al-Dawasir

20CriticalTrigger

Deed not received by the end of December

Contingency

Move to the fallback site and adapt the design

Impact

Design and tender suspended; training and skills testing in the governorate stay in temporary premises for at least six more months

SAR 12M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
9Medium

Exposure

SAR 12M

Residual

⁦55⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 22 days ago

  1. Project manager

    Eng. Shahad M. Al-Malki

    Currently followed up here
  2. Programme manager

    Eng. Shahad M. Al-Malki

    Automatically at 15 days unreviewed · threshold passed 7 days ago
  3. PMO director

    Current level

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · threshold passed 2 days ago
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A letter from the Secretary-General to the owning body

    Dr. Abdullah S. Al-QahtaniDr. Abdullah S. Al-QahtaniSecretary-GeneralP-001a.alqahtani@sca.sa
    Done⁦2026-10-25⁩2026-10-2514 Jumada I 1448 AH
  • Identify a fallback plot with the governorate municipality

    Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa
    Not startedIn 48 days2026-12-156 Rajab 1448 AH

Trigger

Deed not received by the end of December

Contingency

Move to the fallback site and adapt the design

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close