Late land allocation and handover stalls the exit from leased premises
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
Programme · PG-05 · Academy & Qualification Centres Portfolio
The Academy campus in Riyadh and the Wadi Al-Dawasir centre instead of leased training venues.
incl. SAR 18M programme reserve
52% of budget
Estimate at completion
Planned 45%
Cost performance index 0.86
Manager
Eng. Shahad M. Al-Malki
Director, Academy Facilities
Sponsor
Eng. Abdulrahman S. Al-Harbi
Dean, SCA Academy
Projects
2 projects
2024-02-04 — 2028-12-31
Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
End the leased training venues in Riyadh by 2028 with the SCA Academy campus
A permanent home for the Wadi Al-Dawasir qualification centre
Bring training and test halls together in owned buildings with one point of access for trainees
Serves strategic objectives
From baseline to target
Annual lease savings
by 2028Training halls moved into owned buildings
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Wadi Al-Dawasir centre uses the standard training-hall design approved for the Riyadh campus
Risks that hit more than one project, managed at programme level.
Late land allocation and handover stalls the exit from leased premises
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 2 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Contractor satisfaction with branch and service-centre service
71%
+1
Target 72%99%
Savings from spend rationalisation
61SAR M
+6
Target 8572%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Wadi Al-Dawasir centre on hold until the land is handed over
Project Approval Committee · 2026-10-22 · DEC-2026-041
Academy campus extension deferred pending the independent engineer’s report
Change Committee · 2026-10-21 · DEC-2026-040
Academy campus contractor claims referred to dispute resolution
Projects Steering Committee · 2026-10-13 · DEC-2026-037
Temporary training building cancelled in favour of the Academy campus
Executive Committee · 2026-09-08 · DEC-2026-044
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| SCA Academy Campus, RiyadhPRJ-2026-007 | Eng. Shahad M. Al-Malki | 4Execution | Critical | 57% | 640M | 780.5M+22.0% | 0.70Schedule performance index · 0.70 | 0.82Cost performance index · 0.82 |
| Wadi Al-Dawasir Vocational Qualification CentrePRJ-2026-033 | Eng. Shahad M. Al-Malki | 3Planning | On hold | 2% | 210M | 210M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 2 | 850M | 990.5M |
SAR 850M
Budget
| Category | Value | Share |
|---|---|---|
| SCA Academy Campus, Riyadh | SAR 640M | 75% |
| Wadi Al-Dawasir Vocational Qualification Centre | SAR 210M | 25% |
| Total | SAR 850M | 100% |