Saudi Contractors AuthorityMunjaz11My actionsNotifications

Portfolio · PF-CAP

Academy & Qualification Centres Portfolio

Off track

The SCA Academy campus in Riyadh, the Jeddah branch and centre, and the qualification centres in Hail and Wadi Al-Dawasir.

What-if scenarios
Approved budget
SAR 1.3B

incl. SAR 46M unallocated reserve

Actual spend
SAR 658.2M

⁦49%⁩ of budget

EAC
SAR 1.5B+9.9%

Estimate at completion

Expected value
SAR 1.9B

⁦1%⁩ realised

Health score
52−9

was ⁦61⁩ in May

Manager

Eng. Abdulrahman S. Al-Harbi

Dean, SCA Academy

Owner

Eng. Turki A. Al-Anazi

Head, Qualification & Training Sector

Programmes4 projects

Academy Owned Premises Programme⁦31%⁩Branches & Regional Centres Programme⁦45%⁩
At risk 1Off track 1Critical 1On hold 1

AI insight

⁦3⁩ projects in this portfolio are pulling its health down

Most of it comes from “SCA Academy Campus, Riyadh” (SPI ⁦0.70⁩) and “Jeddah Branch & Qualification Centre” (SPI ⁦0.78⁩). Fixing those two lifts the portfolio towards ⁦61⁩ within two quarters.

Confidence⁦81%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
SCA Academy Campus, Riyadh89.0⁦27.3%⁩⁦57%⁩⁦15.6%⁩
Jeddah Branch & Qualification Centre82.0⁦25.2%⁩⁦39%⁩⁦9.8%⁩
Hail Vocational Qualification Centre80.0⁦24.5%⁩⁦52%⁩⁦12.8%⁩
Wadi Al-Dawasir Vocational Qualification CentreSuspended — progress frozen75.0⁦23.0%⁩⁦1%⁩⁦0.2%⁩
Portfolio progress⁦38.4%⁩

How it is computed

⁦38.4%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦0⁩
  • · For comparison: weighting by budget alone gives ⁦43.5%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

52Off track
DimensionScoreWeightPoints
Schedule42⁦20%⁩8.4
Cost50⁦20%⁩10.0
Risk30⁦15%⁩4.5
Scope64⁦10%⁩6.4
Quality75⁦10%⁩7.5
Resources58⁦10%⁩5.8
Stakeholders60⁦5%⁩3.0
Benefits64⁦10%⁩6.4
Total52

Health-score trend

May – October 2026

6152

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • At risk
  • Off track
  • Critical
  • On hold
Approved budget · SAR 640M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1SCA Academy Campus, RiyadhPRJ-2026-007·Priority score 81Critical
  2. 2Jeddah Branch & Qualification CentrePRJ-2026-006·Priority score 79Off track
  3. 3Hail Vocational Qualification CentrePRJ-2026-019·Priority score 73At risk
  4. 4Wadi Al-Dawasir Vocational Qualification CentrePRJ-2026-033·Priority score 61On hold

Portfolio priorities 2026–2027

  • Stop the schedule bleed on the SCA Academy campusSPI at 0.70 and the contractor’s claims are open before the steering committee.
  • End leased training venues by 2028The portfolio’s largest return — recurring annual lease savings.
  • Hand over the Jeddah branch and centre before the end of 2027A commitment to the Secretary-General and the board to serve contractors in the Western & Southern region.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 1.3BSAR 1.3B
Unallocated reserve−SAR 46MSAR 1.3B
Academy Owned Premises Programme+SAR 140.5MSAR 1.4B
Branches & Regional Centres Programme+SAR 38.6MSAR 1.5B
Estimate at completionSAR 1.5BSAR 1.5B

Budget use

658.2M/ 1.3B133.1Mprojected overrun(⁦9.9%⁩)
Actual spend
658.2M
Committed
1B
Approved budget
1.3B
Estimate at completion
1.5B

Expected-value mix

Expected-value mix

SAR 1.9B

Expected value

  • Cost savingSAR 874M⁦46%⁩
  • Beneficiary satisfactionSAR 570M⁦30%⁩
  • Sustainability (ESG)SAR 266M⁦14%⁩
  • RevenueSAR 190M⁦10%⁩
Expected-value mix
CategoryValueShare
Cost savingSAR 874M⁦46%⁩
Beneficiary satisfactionSAR 570M⁦30%⁩
Sustainability (ESG)SAR 266M⁦14%⁩
RevenueSAR 190M⁦10%⁩
TotalSAR 1.9B⁦100%⁩

SAR 21.5M

Expected value SAR 1.9B

⁦34%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦4⁩ results
Export CSV
SCA Academy Campus, RiyadhPRJ-2026-007PG-054ExecutionCritical⁦57%⁩⁦27.3%⁩P1P1 · Top priority — score ⁦81⁩ of 100640M780.5M⁦+22.0%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82Risk score · Weak
Jeddah Branch & Qualification CentrePRJ-2026-006PG-064ExecutionOff track⁦39%⁩⁦25.2%⁩P1P1 · Top priority — score ⁦79⁩ of 100286M321.3M⁦+12.4%⁩0.78Schedule performance index · 0.780.89Cost performance index · 0.89Risk score · Weak
Wadi Al-Dawasir Vocational Qualification CentrePRJ-2026-033PG-053PlanningOn hold⁦2%⁩⁦23.0%⁩P2P2 · High priority — score ⁦61⁩ of 100210M210M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Weak
Hail Vocational Qualification CentrePRJ-2026-019PG-064ExecutionAt risk⁦52%⁩⁦24.5%⁩P2P2 · High priority — score ⁦73⁩ of 100158M161.2M⁦+2.0%⁩0.93Schedule performance index · 0.930.98Cost performance index · 0.98Risk score · Good
Total · 41.3B1.5B
⁦1⁩–⁦4⁩ of ⁦4⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Latest on this portfolio

Yesterday27 October 2026

  1. Approval: Bid Evaluation & Award Committee Approved DEC-2026-043Replacement bank guarantee for the Jeddah branch contractor accepted

    2026-10-27 10:00

22 October 2026

  1. Rejection: Project Approval Committee Hold DEC-2026-041Wadi Al-Dawasir centre on hold until the land is handed over

    2026-10-22 10:00

21 October 2026

13 October 2026

  1. Approval: Projects Steering Committee Approved DEC-2026-037Academy campus contractor claims referred to dispute resolution

    2026-10-13 10:00

8 September 2026

  1. Rejection: Executive Committee Cancel DEC-2026-044Temporary training building cancelled in favour of the Academy campus

    2026-09-08 10:00

21 April 2026

  1. Approval: Change Committee Approved DEC-2026-033Variation to redesign the Jeddah centre training halls approved

    2026-04-21 10:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close