AI insight
No early warning on this project
Only a 38% chance of a further slip on current trends.
A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
85
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 38% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 52% done against 56% planned.
SPI 0.93, CPI 0.98.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-3.1.1Branches & regional centres
The project’s share of the initiative’s project budget (2 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
52%Awaiting acceptance 11%
Not handed in 37%
6 deliverables accepted
1 deliverable under inspection or acceptance
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 83% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 2.1M
Impact
0 escalated
6 of 12 approved
1 member