Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−11

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦52%⁩ done against ⁦56%⁩ planned.

SPI ⁦0.93⁩, CPI ⁦0.98⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.3A better contractor experience and service quality

Main initiative

SI-3.1.1Branches & regional centres

Contribution to the initiative⁦36%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-019
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦52%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦37%⁩

6 deliverables accepted

  • Site works & excavation⁦15%⁩
  • Structure⁦15%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Finishes⁦11%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦83%⁩ of budget

83.8M/ 158M3.2Mprojected overrun(⁦2.0%⁩)
Actual spend
83.8M
Committed
131M
Approved budget
158M
Estimate at completion
161.2M

Next milestones

  • Provisional acceptance⁦2027-01-11⁩was ⁦2027-01-02⁩At risk
  • Closure⁦2027-03-12⁩was ⁦2027-02-28⁩At risk

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 2.1M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0039Late supply of training-hall audio-visual systemsProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦12⁩ approved

  • Project plan & baseline019-D1 · V1 · CRT-019-01⁦4%⁩Eng. Fahad T. Al-Sulami⁦2025-06-15⁩2025-06-1519 Dhuʻl-Hijjah 1446 AHApproved
  • Monitoring & reporting019-D2 · V1 · CRT-019-02⁦4%⁩Eng. Abdulrahman S. Al-Harbi⁦2025-08-10⁩2025-08-1016 Safar 1447 AHApproved
  • Detailed design019-D3 · V1 · CRT-019-03⁦7%⁩Eng. Abdulrahman S. Al-Harbi⁦2025-10-06⁩2025-10-0614 Rabiʻ II 1447 AHApproved
  • Permits & approvals019-D4 · V1 · CRT-019-04⁦7%⁩Eng. Turki A. Al-Anazi⁦2025-12-02⁩2025-12-0211 Jumada II 1447 AHApproved
  • Site works & excavation019-D5 · V1 · CRT-019-05⁦15%⁩Eng. Turki A. Al-Anazi⁦2026-01-27⁩2026-01-278 Shaʻban 1447 AHApproved
  • Structure019-D6 · V1 · CRT-019-06⁦15%⁩Eng. Fahad T. Al-Sulami⁦2026-03-25⁩2026-03-256 Shawwal 1447 AHApproved
  • Finishes019-D7 · V1⁦11%⁩Eng. Abdulrahman S. Al-Harbi160 days overdue2026-05-214 Dhuʻl-Hijjah 1447 AHIn review
  • Supply019-D8 · V0⁦9%⁩Eng. Fahad T. Al-Sulami104 days overdue2026-07-162 Safar 1448 AHDraft
  • Installation019-D9 · V0⁦8%⁩Eng. Abdulrahman S. Al-Harbi47 days overdue2026-09-1129 Rabiʻ I 1448 AHDraft
  • Testing & commissioning019-D10 · V0⁦8%⁩Eng. Turki A. Al-AnaziIn 10 days2026-11-0727 Jumada I 1448 AHDraft
  • Provisional acceptance019-D11 · V0⁦6%⁩Eng. Abdulrahman S. Al-HarbiIn 66 days2027-01-0224 Rajab 1448 AHDraft
  • Final acceptance019-D12 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 123 days2027-02-2821 Ramadan 1448 AHDraft

Team, contracts & documents

Team

1 member

Eng. Fahad T. Al-Sulami · Director, Regional Qualification Centres
  • Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresProject managerP-023f.alsulami@sca.sa⁦45%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close