PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Electronic forms

The project’s twelve forms with their status and approval path, each printable with its approval log.

Forms

16

In approval

1

Past their limit

1

Escalated automatically

0

Approved

14

1SCA-PMO-F01Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

ApprovedV2 · ⁦2024-08-18⁩

2SCA-PMO-F02Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

ApprovedV4 · ⁦2024-10-12⁩

3SCA-PMO-F03Approval

Project weight

The weight and the relative weight in the portfolio

ApprovedV2 · ⁦2026-09-16⁩

4SCA-PMO-F04Initiation

Project charter

Objective, scope, deliverables, roles and budget

ApprovedV2 · ⁦2025-03-14⁩

5SCA-PMO-F05Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

ApprovedV2 · ⁦2025-04-10⁩

6SCA-PMO-F06Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

ApprovedV1 · ⁦2025-03-23⁩

9SCA-PMO-F09Execution

Change request

The change, its impact analysis and the approval decision

Not yet · Opens at the «Execution» stage

10SCA-PMO-F10Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Not yet · Opens at the «Execution» stage

11SCA-PMO-F11Execution

Corrective plan

Actions, owners, dates and status

Not yet · Opens at the «Execution» stage

12SCA-PMO-F12Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Not yet · Opens at the «Closure» stage