Execution
Periodic update card
Progress, status, risks and support requested
- Form no.
- SCA-PMO-F07
- Template edition
- 2.2
- Version
- V1
- Form date
- 2026-09-02
- Hijri
- 20 Rabiʻ I 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-019
- Project
- Hail Vocational Qualification Centre
- Portfolio
- Academy & Qualification Centres Portfolio
- Sector
- Qualification & Training Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Fahad T. Al-Sulami
1ProgressAuto-filled
From the live data: accepted deliverables, the schedule and finance on the period’s last day.
Actual progress
46%
Planned to date
49%
SPI
0.95
Actual cost
SAR 73.8M
Main achievements this periodFilled by the project manager
Work went to the approved plan for the period, with the due deliverables handed in.
2Status
- Overall healthAuto-filled
- At risk
- StageAuto-filled
- Execution
- Forecast finishAuto-filled
- 2027-03-12
The PM’s comment on the statusFilled by the project manager
The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.
3Risks and impedimentsAuto-filled
| Code | Risk | Score | Owner |
|---|---|---|---|
| RSK-0039 | Late supply of training-hall audio-visual systems | 9 | Eng. Fahad T. Al-Sulami |
| Code | Impediment | Severity |
|---|---|---|
| No open impediments | ||
4Support requested
What the project needs from leadership or the committeesFilled by the project manager
Approve change request CR-2026-012 for three integration engineers (SAR 980K), and the Secretary-General to press the NIC on the Nafath environment.
- Includes financial supportAuto-filled
- Yes
Approval logChain: Periodic update approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Fahad T. Al-SulamiDirector, Regional Qualification Centres | Submitted | — | 2026-09-02 14:05 |
| 2 | PMO check | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | The reading agrees with the schedule and finance. | 2026-09-06 14:23 |
| 3 | Sponsor review & approval | Technical acceptance | Eng. Turki A. Al-AnaziProject sponsor | Approved | — | 2026-09-07 09:30 |
Signatures
PMO check
Ghada A. Al-Shahrani
Approved2026-09-06
Sponsor review & approval
Eng. Turki A. Al-Anazi
Approved2026-09-07