Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

A new ⁦18,000⁩ m² training and skills-test centre for the contracting workforce in Hail, with ⁦12⁩ halls and a practical workshop.

In scope

  • A new ⁦18,000⁩ m² training and skills-test centre for the contracting workforce in Hail, with ⁦12⁩ halls and a practical workshop.
  • Saudi Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-04-19⁩

    Baseline approved at the planning gate

    Budget158MFinish⁦2027-02-28⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-019-01A building ready for training and testingBusinessMustApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.saSB-1
REQ-019-02Match the approved drawingsTechnicalMustIn progressEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.saSB-1
REQ-019-03Smart building systemsFunctionalMustIn progressEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.saSB-1
REQ-019-04Saudi Building CodeRegulatoryCouldApprovedEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.saSB-1
REQ-019-05Health & safetyRegulatoryCouldApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.saSB-1
REQ-019-06CCTV and access controlSecurityShouldIn progressEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close