PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 158M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 3.2M
EAC SAR 161.2M
Revised request SAR 158M
  • Actual spendSAR 83.8M
  • Committed, not spentSAR 47.2M
  • Allotted, uncommittedSAR 22.3M
  • Contingency availableSAR 4.7M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 145.4M
Original budgetwhen the first baseline was approved
SAR 158M
Approved budgetafter approved change requests
SAR 158M
Current budgetavailable to spend now
SAR 158M
Revised budgetif the pending changes are approved
SAR 158M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 131M
Contracts1 active contract
SAR 118M
Purchase orders⁦3⁩ orders
SAR 13M
Remaining budgetapproved less actual
SAR 74.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 83.8M
Accrualswork done, not yet invoiced
SAR 3.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 161.2M
ContingencySAR 3.2M drawn of SAR 7.9M
SAR 4.7M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 145.4M
ApprovedSAR 158M
Estimate at completionSAR 161.2M
Approved is SAR 12.6M (⁦8.7%⁩) above the estimate
The estimate at completion is SAR 15.8M (⁦10.9%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-12-31⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51019
  • WBS elements⁦5⁩ elements · P-2026-019.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦10⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 3.2M drawn of SAR 7.9M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 3.2M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance9.209.689.689.68⁦−0.49⁩
2Design & permits18.3919.3719.3719.37⁦−0.98⁩
3Civil works58.2457.0854.7958.44⁦−0.20⁩
4MEP works45.9830.590.0048.66⁦−2.68⁩
5Handover21.4614.280.0022.71⁦−1.25⁩
Unallocated contingency4.740.000.002.37⁦+2.37⁩
Total158.00131.0083.84161.22⁦−3.22⁩

Budget split

WBS

SAR 158M

Budget

  • Management & governanceSAR 9.2M⁦6%⁩
  • Design & permitsSAR 18.4M⁦12%⁩
  • Civil worksSAR 58.2M⁦37%⁩
  • MEP worksSAR 46M⁦29%⁩
  • HandoverSAR 21.5M⁦14%⁩
  • Unallocated contingencySAR 4.7M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-18⁩+445

SPI(t) ⁦0.62⁩ against the approved finish ⁦2027-02-28⁩

Planned valuePV
SAR 146.3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 82.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 83.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 158M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−1.68⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−64.14⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.98
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.56
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 161.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 77.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−3.22⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.02
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 161.2M
  • If the rest goes to planSAR 159.7M
  • At cost and schedule performanceSAR 221.6M
  • The PM’s bottom-up estimateSAR 161.2M
  • To stay within SAR 158M, cost performance on the rest must rise to ⁦1.02⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 161.2M

Variance at completion: ⁦−3.22⁩ SAR M