PRJ-2026-019At risk4ExecutionConstruction
Hail Vocational Qualification Centre
Add to watchlistA new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.
Project managerEng. Fahad T. Al-SulamiProject sponsorEng. Turki A. Al-AnaziProgrammeBranches & Regional Centres Programme
Budget (BAC)
SAR 158M
Actual cost
SAR 83.8M
53% of budget
Progress
52%Awaiting acceptance 11%
Estimate at completion
SAR 161.2M
SAR +3.2M
SPI · CPI
0.93Schedule performance index · 0.930.98Cost performance index · 0.98
Forecast finish
2027-03-12
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started