Hail Vocational Qualification Centre
Add to watchlistA new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.
Budget (BAC)
Actual cost
53% of budget
Progress
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure2 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started