Rising prices of imported training-hall fit-out and audio-visual systems
PRK-06-1·Transfer·Eng. Fahad T. Al-Sulami
Programme · PG-06 · Academy & Qualification Centres Portfolio
The Jeddah branch and centre, and the Hail qualification centre.
incl. SAR 12M programme reserve
46% of budget
Estimate at completion
Planned 53%
Cost performance index 0.92
Manager
Eng. Fahad T. Al-Sulami
Director, Regional Qualification Centres
Sponsor
Eng. Abdulrahman S. Al-Harbi
Dean, SCA Academy
Projects
2 projects
2024-09-01 — 2027-07-04
At risk 1Off track 1
What the programme must achieve, and the strategic objectives it serves.
Bring SCA services and qualification programmes closer to regional contractors with fit-for-purpose centres in Jeddah and Hail
40 training & test halls at the Jeddah branch equipped for e-testing
Reception areas and service centres worthy of contractors in both buildings
From baseline to target
Waiting space per visitor at peak
by 2027Contractor satisfaction with branch service
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The Hail centre reuses the e-test hall design approved for Jeddah
Risks that hit more than one project, managed at programme level.
Rising prices of imported training-hall fit-out and audio-visual systems
PRK-06-1·Transfer·Eng. Fahad T. Al-Sulami
3 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Skills tests held per month
4.1thousand tests
0
Target 4.591%
Contractor satisfaction with branch and service-centre service
71%
+1
Target 72%99%
Contracts won by Irtiqaa beneficiaries (cumulative)
1,810SAR M
+230
Target 2,40075%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
Members
5 members
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Jeddah Branch & Qualification CentrePRJ-2026-006 | Eng. Fahad T. Al-Sulami | 4Execution | Off track | 39% | 286M | 321.3M+12.4% | 0.78Schedule performance index · 0.78 | 0.89Cost performance index · 0.89 |
| Hail Vocational Qualification CentrePRJ-2026-019 | Eng. Fahad T. Al-Sulami | 4Execution | At risk | 52% | 158M | 161.2M+2.0% | 0.93Schedule performance index · 0.93 | 0.98Cost performance index · 0.98 |
| Total · 2 | 444M | 482.6M |
SAR 444M
Budget
| Category | Value | Share |
|---|---|---|
| Jeddah Branch & Qualification Centre | SAR 286M | 64% |
| Hail Vocational Qualification Centre | SAR 158M | 36% |
| Total | SAR 444M | 100% |