Project status card
28 October 2026 · 17 Jumada I 1448 AH
Hail Vocational Qualification Centre
PRJ-2026-019 · Qualification & Training Sector · Strategic · WP-2025-019
- Progress
- 52% / 56%
- SPI · CPI
- 0.93 · 0.98
- Spend
- SAR 83.8M / SAR 158M
- Estimate at completion
- SAR 161.2M
Schedule
Planned to date 56%
Forecast finish: 2027-03-124 Shawwal 1448 AH · 12 days late
SPI0.93Schedule performance index · 0.93CPI0.98Cost performance index · 0.98Health dimensions
Last update: 2026-10-2514 Jumada I 1448 AH · Up to date
Deliverables
6 of 9 due deliverables accepted on time (67%)
Next milestones
- Build complete2026-11-2616 Jumada II 1448 AH
- Testing & acceptance complete2027-01-2820 Shaʻban 1448 AH
- Final handover2027-03-113 Shawwal 1448 AH
Top risks
- Late supply of training-hall audio-visual systems9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 158M: 0 on track and 0 red or critical. Weighted progress is 52% against 56% planned, spend SAR 83.8M, and EAC SAR 161.2M (SAR 3.2M over).
No project is more than a month behind baseline.