Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Hail Vocational Qualification Centre

PRJ-2026-019 · Qualification & Training Sector · Strategic · WP-2025-019

At risk4ExecutionProject manager: Eng. Fahad T. Al-Sulami · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦52%⁩ / ⁦56%⁩
SPI · CPI
0.93 · 0.98
Spend
SAR 83.8M / SAR 158M
Estimate at completion
SAR 161.2M

Schedule

⁦4%⁩ behind⁦52%⁩

Planned to date ⁦56%⁩

Forecast finish: 2027-03-124 Shawwal 1448 AH · 12 days late

SPI0.93Schedule performance index · 0.93CPI0.98Cost performance index · 0.98

Health dimensions

At risk

Last update: 2026-10-2514 Jumada I 1448 AH · Up to date

Deliverables

⁦6⁩ of ⁦9⁩ due deliverables accepted on time (⁦67%⁩)

Next milestones

  • Build complete2026-11-2616 Jumada II 1448 AH
  • Testing & acceptance complete2027-01-2820 Shaʻban 1448 AH
  • Final handover2027-03-113 Shawwal 1448 AH

Top risks

  • Late supply of training-hall audio-visual systems9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 158M: 0 on track and 0 red or critical. Weighted progress is 52% against 56% planned, spend SAR 83.8M, and EAC SAR 161.2M (SAR 3.2M over).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Fahad T. Al-Sulami in MunjazInternal

Status: At risk ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close