PRJ-2026-019At risk4ExecutionConstruction

Hail Vocational Qualification Centre

Add to watchlist

A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-03-23⁩
Hijri
23 Ramadan 1446 AH
ApprovedMTG-KO-019Kick-off — Hail Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-019
Project
Hail Vocational Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Fahad T. Al-Sulami

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Hail Vocational Qualification Centre
Date and timeAuto-filled
⁦2025-03-23⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Eng. Fahad T. Al-Sulami

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Turki A. Al-AnaziHead, Qualification & Training Sector
Eng. Abdulrahman S. Al-HarbiDean, SCA Academy
Eng. Fahad T. Al-SulamiDirector, Regional Qualification Centres
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Eng. Turki A. Al-AnaziProject sponsorSponsors the project, decides escalations and material changes
Eng. Abdulrahman S. Al-HarbiProject ownerApproves the requirements and accepts the deliverables
Eng. Fahad T. Al-SulamiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Fahad T. Al-Sulami⁦2025-08-10⁩Done
Designs approvedEng. Fahad T. Al-Sulami⁦2025-12-02⁩Done
Build completeEng. Fahad T. Al-Sulami⁦2026-05-21⁩Open
Testing & acceptance completeEng. Fahad T. Al-Sulami⁦2026-11-07⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-07-08⁩
Start confirmed
Eng. Turki A. Al-Anazi · ⁦2025-03-24⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiDirector, Regional Qualification CentresSubmitted—⁦2025-03-24⁩ 09:54
2Chair’s approval (sponsor)Technical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2025-03-25⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-03-25⁩ 13:58

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-03-25⁩

Chair’s approval (sponsor)

Eng. Turki A. Al-Anazi

Approved⁦2025-03-25⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2025-03-24⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-03-25⁩ at ⁦13:58⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2025-03-25⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-03-23⁩

    The minutes as taken

    Eng. Fahad T. Al-Sulami

Only one version so far.