Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- SCA-PMO-F01
- Template edition
- 2.1
- Version
- V2
- Form date
- 2024-08-18
- Hijri
- 14 Safar 1446 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-019
- Project
- Hail Vocational Qualification Centre
- Portfolio
- Academy & Qualification Centres Portfolio
- Sector
- Qualification & Training Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Fahad T. Al-Sulami
1The proposalAuto-filled
- TitleAuto-filled
- Hail Vocational Qualification Centre
- Proposed byAuto-filled
- Eng. Fahad T. Al-Sulami
- DepartmentAuto-filled
- Regional Qualification Centres Department
- Submitted onAuto-filled
- 2024-08-18
- Proposal numberAuto-filled
- DMD-2026-019
2Justification
A new 18,000 m² training and skills-test centre for the contracting workforce in Hail, with 12 halls and a practical workshop.
3Objectives
- A better contractor experience and service quality
Strategic objectives served
- SO-3.3 — A better contractor experience and service quality
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SAR 158M
Funding
The owning sector’s approved budget
| Cost line | Amount |
|---|---|
| Main contract | SAR 113.8M |
| Supervision & consulting | SAR 22.1M |
| Internal team | SAR 14.2M |
| Contingency reserve (5%) | SAR 7.9M |
| Total | SAR 158M |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| Late supply of training-hall audio-visual systems | Medium | Treated in the risk management plan |
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Fahad T. Al-SulamiDirector, Regional Qualification Centres | Submitted | — | 2024-08-18 12:57 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Reem K. Al-DosariThe requester’s line manager | Approved | — | 2024-08-20 10:07 |
| 3 | PMO review | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2024-08-25 11:14 |
| 4 | Portfolio manager review | Technical acceptance | Eng. Abdulrahman S. Al-HarbiPortfolio manager | Approved | Consistent with the portfolio plan and its priorities. | 2024-08-26 12:21 |
| 5 | Cost & funding review | Financial approval | Approval engineFinance | Pre-breach alert | — | 2024-08-29 08:00 |
| 6 | Cost & funding review | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2024-09-01 12:33 |
| 7 | Project Approval Committee | Technical acceptance | Dr. Noura M. Al-OtaibiProject Approval Committee | Approved | — | 2024-09-02 14:35 |
Signatures
Line manager endorsement
Eng. Reem K. Al-Dosari
Approved2024-08-20
PMO review
Ghada A. Al-Shahrani
Approved2024-08-25
Portfolio manager review
Eng. Abdulrahman S. Al-Harbi
Approved2024-08-26
Cost & funding review
Munirah A. Al-Khalidi
Approved2024-09-01
Project Approval Committee
Dr. Noura M. Al-Otaibi
Approved2024-09-02