RSK-0026SCA Academy Campus, Riyadh
Contractor financial claims piling up over unapproved variations
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Variations carried out before formal approval, and disputes over their pricing
Preventive controls
- Refer the claims to the dispute board named in the contract
- List every unapproved variation with the independent engineer
1 / 2
Event
Contractor financial claims piling up over unapproved variations
A dispute-board recommendation above SAR 25M
Contingency
An amicable settlement within a ceiling set by the projects steering committee
Impact
Claims that could reach SAR 41M and a strained contract relationship
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 41M
Residual
40% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 3 days ago
Project manager
Eng. Shahad M. Al-Malki
Currently followed up hereProgramme manager
Current levelEng. Shahad M. Al-Malki
Automatically at 15 days unreviewed · in 12 days- 3
PMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 17 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Refer the claims to the dispute board named in the contract
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.saDone2026-10-132026-10-132 Jumada I 1448 AHList every unapproved variation with the independent engineer
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saIn progressIn 13 days2026-11-1030 Jumada I 1448 AH
Trigger
A dispute-board recommendation above SAR 25M
Contingency
An amicable settlement within a ceiling set by the projects steering committee