CR-2026-005SCA Academy Campus, Riyadh

Variation 7: revise the central HVAC system

ContractEscalatedImpact level: Major55 days overdue2026-09-0321 Rabiʻ I 1448 AH

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 18.6M

Current budgetSAR 640M

After the changeSAR 658.6M

+2.9%

Schedule

+⁦40⁩ d
  • Baseline finish2026-12-31
  • New finish2027-02-09

Risk

−4

Benefits

+4%

14% less energy a year

⁦+4⁩% of expected benefits

Reason for change

Central HVAC loads insufficient after extra training halls and a main lecture hall were added

Justification

Without it the building fails the Saudi Energy Code

PMO recommendation

Defer

The pricing dispute was referred to the projects steering committee

Approval workflow

  1. Submitted

    Eng. Shahad M. Al-Malki

    Done2026-08-20

  2. PM review

    Eng. Shahad M. Al-Malki

    Done2026-08-21

  3. Impact analysis

    Karim Haddad

    Done2026-08-25

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-08-26

  5. 5

    Change committee recommendation

    Dr. Mohammed I. Al-Subaie

    Escalated2026-10-13

  6. 6

    Executive Committee decision

    Dr. Abdullah S. Al-Qahtani

    Now

  7. 7

    Baseline updated

    Eng. Shahad M. Al-Malki

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SAR 5M or 90 days

  • A cost impact of SAR 18.6M is above SAR 5M — «major»: the Change Committee recommends and the Executive Committee decides.
  • It touches a signed contract, so Finance & Procurement review it contractually.

Awaiting the Executive Committee’s decision

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Steering Committee — October13 October 2026 10:00Main Conference Hall — Headquarters
  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairApprove with conditions
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saReject
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saReject
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove with conditions
6/6Quorum met
  • Approve2
  • Approve with conditions2
  • Reject2
  • Abstain0

Awaiting the impact analysis