AI insight
97% chance of a further slip within 30 days
From the SPI trend (0.70), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
47
Critical
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.70), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 57% done against 82% planned.
SPI 0.70, CPI 0.82.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-4.3.1Owned premises for the Academy
The project’s share of the initiative’s project budget (1 project)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
57%Awaiting acceptance 10%
Not handed in 33%
7 deliverables accepted
1 deliverable under inspection or acceptance
Corrective planCP-2026-03
Awaiting approvalOverdue: 1
Unapproved curtain-wall samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7
Actions
0 of 4 done
Next: Rule on the façade samples or approve an equivalent · Eng. Shahad M. Al-Malki · 2026-10-15
Days won back
0 of 60
With the plan: 2027-06-01
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 97% of budget
3 approvals and 3 open actions on this project
From «My actions» for this project
3 open
Cost and schedule impact
3 open risks, exposure SAR 65.5M
Impact
2 escalated
7 of 12 approved
4 members