Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−24

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦97%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.70⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦57%⁩ done against ⁦82%⁩ planned.

SPI ⁦0.70⁩, CPI ⁦0.82⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.3A sustainable financial base

Main initiative

SI-4.3.1Owned premises for the Academy

Contribution to the initiative⁦100%⁩

The project’s share of the initiative’s project budget (1 project)

Secondary links

Annual work-plan line
WP-2024-007
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦57%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦33%⁩

7 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Supply⁦10%⁩

Corrective planCP-2026-03

Awaiting approvalOverdue: ⁦1⁩

Unapproved curtain-wall samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7

Actions

⁦0⁩ of ⁦4⁩ done

Next: Rule on the façade samples or approve an equivalent · Eng. Shahad M. Al-Malki · 2026-10-15

Days won back

⁦0⁩ of ⁦60⁩

With the plan: 2027-06-01

Open the plan

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦97%⁩ of budget

444.9M/ 640M140.5Mprojected overrun(⁦22.0%⁩)
Actual spend
444.9M
Committed
618M
Approved budget
640M
Estimate at completion
780.5M

Next milestones

  • Provisional acceptance⁦2027-01-29⁩was ⁦2026-10-07⁩Late
  • Closure⁦2027-06-01⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦3⁩ approvals and ⁦3⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦3⁩ open

  • Prepare the claims file for the dispute boardEng. Shahad M. Al-MalkiIn 9 days2026-11-0626 Jumada I 1448 AHHigh
  • Approve or reject the façade samples with reasonsEng. Ibrahim A. Al-Ghamdi13 days overdue2026-10-154 Jumada I 1448 AHCritical
  • Commission an independent engineer to assess the ⁦150-day⁩ extensionEng. Abdulrahman S. Al-HarbiIn 7 days2026-11-0424 Jumada I 1448 AHHigh

Risks & impediments

3 open risks, exposure SAR 65.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0026Contractor financial claims piling up over unapproved variationsProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0027Late delivery of curtain-wall glazing from the overseas factoryProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0028Possible removal of the MEP subcontractor
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High2
  • Medium0
  • Low0

Deliverables

⁦7⁩ of ⁦12⁩ approved

  • Project plan & baseline007-D1 · V1 · CRT-007-01⁦3%⁩Eng. Shahad M. Al-Malki⁦2024-06-18⁩2024-06-1812 Dhuʻl-Hijjah 1445 AHApproved
  • Monitoring & reporting007-D2 · V1 · CRT-007-02⁦3%⁩Eng. Abdulrahman S. Al-Harbi⁦2024-09-10⁩2024-09-107 Rabiʻ I 1446 AHApproved
  • Detailed design007-D3 · V1 · CRT-007-03⁦6%⁩Eng. Abdulrahman S. Al-Harbi⁦2024-12-03⁩2024-12-032 Jumada II 1446 AHApproved
  • Permits & approvals007-D4 · V1 · CRT-007-04⁦6%⁩Eng. Turki A. Al-Anazi⁦2025-02-25⁩2025-02-2526 Shaʻban 1446 AHApproved
  • Site works & excavation007-D5 · V1 · CRT-007-05⁦13%⁩Eng. Turki A. Al-Anazi⁦2025-05-21⁩2025-05-2123 Dhuʻl-Qiʻdah 1446 AHApproved
  • Structure007-D6 · V1 · CRT-007-06⁦13%⁩Eng. Shahad M. Al-Malki⁦2025-08-13⁩2025-08-1319 Safar 1447 AHApproved
  • Finishes007-D7 · V1 · CRT-007-07⁦13%⁩Eng. Abdulrahman S. Al-Harbi⁦2025-11-05⁩2025-11-0514 Jumada I 1447 AHApproved
  • Supply007-D8 · V1⁦10%⁩Eng. Shahad M. Al-Malki273 days overdue2026-01-289 Shaʻban 1447 AHSubmitted
  • Installation007-D9 · V0⁦10%⁩Eng. Abdulrahman S. Al-Harbi189 days overdue2026-04-225 Dhuʻl-Qiʻdah 1447 AHDraft
  • Testing & commissioning007-D10 · V0⁦9%⁩Eng. Turki A. Al-Anazi104 days overdue2026-07-162 Safar 1448 AHDraft
  • Provisional acceptance007-D11 · V0⁦7%⁩Eng. Abdulrahman S. Al-Harbi20 days overdue2026-10-0827 Rabiʻ II 1448 AHDraft
  • Final acceptance007-D12 · V0⁦7%⁩Eng. Turki A. Al-AnaziIn 64 days2026-12-3122 Rajab 1448 AHDraft

Team, contracts & documents

Team

4 members

Eng. Shahad M. Al-Malki · Director, Academy FacilitiesEng. Abdulrahman S. Al-Harbi · Dean, SCA AcademyKhalid N. Al-Mutairi · Senior Finance & Procurement SpecialistEng. Adel S. Al-Amoudi · Senior Site Engineer (Contractor)
  • Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesProject managerP-022s.almalki@sca.sa⁦90%⁩
  • Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyProject sponsorP-014ab.alharbi@sca.sa⁦25%⁩
  • Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistAcademy campus contract & certificatesP-007k.almutairi@sca.sa⁦20%⁩
  • Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)Site engineer (MEP)P-043a.alamoudi@sca.sa⁦40%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close