PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-02-29⁩
Hijri
19 Shaʻban 1445 AH
ApprovedPRJ-2026-007SCA Academy Campus, Riyadh

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-02-04⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2027-06-01⁩

SPI

0.70

MilestonePlannedForecastSlip
Project plan approved⁦2024-09-10⁩⁦2025-01-10⁩+122 days
Designs approved⁦2025-02-25⁩⁦2025-09-29⁩+216 days
Build complete⁦2025-11-05⁩⁦2026-10-26⁩+355 days
Testing & acceptance complete⁦2026-07-16⁩⁦2027-04-15⁩+273 days
Final handover⁦2026-12-31⁩⁦2027-06-02⁩+153 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2024-06-18⁩Eng. Shahad M. Al-Malki
Monitoring & reporting⁦3%⁩⁦2024-09-10⁩Eng. Abdulrahman S. Al-Harbi
Detailed design⁦6%⁩⁦2024-12-03⁩Eng. Abdulrahman S. Al-Harbi
Permits & approvals⁦6%⁩⁦2025-02-25⁩Eng. Turki A. Al-Anazi
Site works & excavation⁦13%⁩⁦2025-05-21⁩Eng. Turki A. Al-Anazi
Structure⁦13%⁩⁦2025-08-13⁩Eng. Shahad M. Al-Malki
Finishes⁦13%⁩⁦2025-11-05⁩Eng. Abdulrahman S. Al-Harbi
Supply⁦10%⁩⁦2026-01-28⁩Eng. Shahad M. Al-Malki
Installation⁦10%⁩⁦2026-04-22⁩Eng. Abdulrahman S. Al-Harbi
Testing & commissioning⁦9%⁩⁦2026-07-16⁩Eng. Turki A. Al-Anazi
Provisional acceptance⁦7%⁩⁦2026-10-08⁩Eng. Abdulrahman S. Al-Harbi
Final acceptance⁦7%⁩⁦2026-12-31⁩Eng. Turki A. Al-Anazi
Accepted with a certificate⁦57%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0026Contractor financial claims piling up over unapproved variations20EscalateEng. Shahad M. Al-Malki
RSK-0027Late delivery of curtain-wall glazing from the overseas factory16MitigateEng. Shahad M. Al-Malki
RSK-0028Possible removal of the MEP subcontractor15MitigateEng. Abdulrahman S. Al-Harbi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Shahad M. Al-Malki
Project ownerDeliverable status and acceptance datesFortnightlyEng. Shahad M. Al-Malki
PMOData and indicator updatesWeeklyEng. Shahad M. Al-Malki
BeneficiariesWhat changes and whenAt each milestoneEng. Shahad M. Al-Malki
Team memberRoleAllocation
Eng. Shahad M. Al-MalkiProject manager⁦90%⁩
Eng. Abdulrahman S. Al-HarbiProject sponsor⁦25%⁩
Khalid N. Al-MutairiAcademy campus contract & certificates⁦20%⁩
Eng. Adel S. Al-AmoudiSite engineer (MEP)⁦40%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Ibrahim A. Al-Ghamdi
Review cadenceAuto-filled
Inspection before every pour; a weekly quality walk with the consultant
Next reviewAuto-filled
⁦2026-11-11⁩
Quality criterionThresholdNowMet
Slab level tolerance±10 mm+27 mm on level 5, building BNo
Roof waterproofingMatches the approved sample; 48 h flood testNot matching on the east roofNo
Inspection requests accepted first time85% or more71%No

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2024-02-29⁩ 11:38
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2024-03-04⁩ 13:10
3Technical acceptance — project ownerTechnical acceptanceEng. Abdulrahman S. Al-HarbiProject ownerApproved—⁦2024-03-07⁩ 14:17
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-03-11⁩ 12:33
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-03-12⁩ 13:10
6Sponsor approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2024-03-17⁩ 11:38

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2024-03-04⁩

Technical acceptance — project owner

Eng. Abdulrahman S. Al-Harbi

Approved⁦2024-03-07⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2024-03-11⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2024-03-12⁩

Sponsor approval

Eng. Turki A. Al-Anazi

Approved⁦2024-03-17⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2024-02-29⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-03-04⁩ at ⁦13:10⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2024-03-07⁩ at ⁦14:17⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-03-11⁩ at ⁦12:33⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-03-12⁩ at ⁦13:10⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2024-03-17⁩ at ⁦11:38⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-02-29⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Shahad M. Al-Malki

  2. V1Returned for edit⁦2024-02-15⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Shahad M. Al-Malki

Esc