Remove from watchlistA 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
In scope
- A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
- Saudi Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2024-03-26
Baseline approved at the planning gate
Budget640MFinish2026-12-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-007-01 | A building ready for training and testing | Business | Must | In progress | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | SB-1 | |
| REQ-007-02 | Match the approved drawings | Technical | Must | In progress | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | SB-1 | |
| REQ-007-03 | Smart building systems | Functional | Must | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | SB-1 | |
| REQ-007-04 | Saudi Building Code | Regulatory | Should | In progress | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | SB-1 | |
| REQ-007-05 | Health & safety | Regulatory | Should | In progress | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | SB-1 | |
| REQ-007-06 | CCTV and access control | Security | Could | In progress | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.