PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦1⁩ of ⁦7⁩ mandatory documents due
  • 6 mandatory documents missing
  • 1 document in the repository

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Present

      Contractor claims file — SCA Academy campusV2

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 007-D1Project plan & baselinePRJ-2026-007_1.1_v1.pdfApprovedDeliverable
  • 007-D2Monitoring & reportingPRJ-2026-007_1.2_v1.pdfApprovedDeliverable
  • 007-D3Detailed designPRJ-2026-007_2.1_v1.pdfApprovedDeliverable
  • 007-D4Permits & approvalsPRJ-2026-007_2.2_v1.pdfApprovedDeliverable
  • 007-D5Site works & excavationPRJ-2026-007_3.1_v1.pdfApprovedDeliverable
  • 007-D6StructurePRJ-2026-007_3.2_v1.pdfApprovedDeliverable
  • 007-D7FinishesPRJ-2026-007_3.3_v1.pdfApprovedDeliverable
  • 007-D8SupplyPRJ-2026-007_4.1_v1.pdfIn reviewDeliverable
  • 007-D9InstallationNo evidence filed yetDraftDeliverable
  • 007-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 007-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 007-D12Final acceptanceNo evidence filed yetDraftDeliverable