SCA Academy Campus, Riyadh
Remove from watchlistA 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-09-10 | 2025-01-10 | +122 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-02-25 | 2025-09-29 | +216 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-11-05 | 2026-10-26 | +355 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-16 | 2027-04-15 | +273 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-06-02 | +153 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
57%Awaiting acceptance
10%Not handed in
33%Deliverable flow
Display options
| Project plan & baseline007-D1 | 3% | CRT-007-01 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2024-06-18 | V1 | 3 of 3 |
| Monitoring & reporting007-D2 | 3% | CRT-007-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2024-09-10 | V1 | 3 of 3 |
| Detailed design007-D3 | 6% | CRT-007-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2024-12-03 | V1 | 3 of 3 |
| Permits & approvals007-D4 | 6% | CRT-007-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-02-25 | V1 | 3 of 3 |
| Site works & excavation007-D5 | 13% | CRT-007-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-05-21 | V1 | 3 of 3 |
| Structure007-D6 | 13% | CRT-007-06 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-13 | V1 | 3 of 3 |
| Finishes007-D7 | 13% | CRT-007-07 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-11-05 | V1 | 3 of 3 |
| Supply007-D8 | 10% | — | Submitted | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-28 | V1 | 1 of 3 |
| Installation007-D9 | 10% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-04-22 | V0 | 0 of 3 |
| Testing & commissioning007-D10 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-07-16 | V0 | 0 of 3 |
| Provisional acceptance007-D11 | 7% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-08 | V0 | 0 of 3 |
| Final acceptance007-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |