PRJ-2026-007Critical4ExecutionConstruction
SCA Academy Campus, Riyadh
Remove from watchlistA 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
Project managerEng. Shahad M. Al-MalkiProject sponsorEng. Turki A. Al-AnaziProgrammeAcademy Owned Premises Programme
Early warning: 97% chance of slipping within 30 days
Budget (BAC)
SAR 640M
Actual cost
SAR 444.9M
70% of budget
Progress
57%Awaiting acceptance 10%
Estimate at completion
SAR 780.5M
SAR +140.5M
SPI · CPI
0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Forecast finish
2027-06-01
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Period
October 2026
In approvalDue todayAction time limit about to lapse · Limit 2 working days
- Progress
- 57%
- Planned
- 82%
- SPI
- 0.70
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-007-2026-10 | In approval | 57% | Methodology reviewDr. Noura M. Al-OtaibiDue todayAction time limit about to lapse · Limit 2 working days | 2026-10-26 |
| September 2026UPD-007-2026-09 | Approved | 54% | — | 2026-10-02 |
| August 2026UPD-007-2026-08 | Approved | 51% | — | 2026-09-02 |