Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Periodic update — October 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
SCA-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-26⁩
Hijri
15 Jumada I 1448 AH
In approvalUPD-007-2026-10Periodic update — October 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦57%⁩

+3 pts on the last period

Planned to date

⁦82%⁩

SPI

0.70

Actual cost

SAR 444.9M

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the September 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
Critical
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-06-01⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

Prefilled from the September 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0026Contractor financial claims piling up over unapproved variations20Eng. Shahad M. Al-Malki
RSK-0027Late delivery of curtain-wall glazing from the overseas factory16Eng. Shahad M. Al-Malki
RSK-0028Possible removal of the MEP subcontractor15Eng. Abdulrahman S. Al-Harbi
CodeImpedimentSeverity
ISS-0109Façade works stopped — samples not approvedCritical
ISS-0110Skilled-labour shortage at the MEP subcontractorHigh
ISS-0111Dispute over the pricing of variation order 7High
ISS-0112Decision on payment certificate 25 delayedMedium

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SAR 980K), and the Secretary-General to press the NIC on the Nafath environment.

Prefilled from the September 2026 card — edit it if it changed

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2026-10-26⁩ 14:11
2PMO checkMethodology reviewApproval enginePMO — analystPre-breach alert—⁦2026-10-28⁩ 08:00

Signatures

PMO check

Ghada A. Al-Shahrani

Awaiting decision

Sponsor review & approval

Eng. Turki A. Al-Anazi

Later

Financial support requested

Munirah A. Al-Khalidi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-10-26⁩

  1. Methodology review

    PMO check

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

    Due todayAction time limit about to lapse · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-28⁩

    Pre-breach alert at ⁦60%⁩ — sent ⁦2026-10-28⁩

  2. Technical acceptance

    Sponsor review & approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Limit 2 working days · Expected by ⁦2026-11-01⁩

  3. Financial approval

    Financial support requested

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-11-03⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-26⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Eng. Shahad M. Al-Malki

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close