Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SAR 640M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-02-04 · by Eng. Turki A. Al-Anazi
A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-02-04 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Shahad M. Al-Malki
What changed from version A to version B
Finish
2026-12-312027-06-02
+153 days
Budget
SAR 640MSAR 640M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference