Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Electronic forms

The project’s twelve forms with their status and approval path, each printable with its approval log.

Forms

19

In approval

4

Past their limit

3

Escalated automatically

1

Approved

15

1SCA-PMO-F01Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

ApprovedV2 · ⁦2023-07-09⁩

2SCA-PMO-F02Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

ApprovedV4 · ⁦2023-09-02⁩

3SCA-PMO-F03Approval

Project weight

The weight and the relative weight in the portfolio

ApprovedV2 · ⁦2026-09-16⁩

4SCA-PMO-F04Initiation

Project charter

Objective, scope, deliverables, roles and budget

ApprovedV2 · ⁦2024-02-02⁩

5SCA-PMO-F05Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

ApprovedV2 · ⁦2024-02-29⁩

6SCA-PMO-F06Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

ApprovedV1 · ⁦2024-02-11⁩

10SCA-PMO-F10Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Not yet · Opens at the «Execution» stage

11SCA-PMO-F11Execution

Corrective plan

Actions, owners, dates and status

In approvalV1 · ⁦2026-10-24⁩
Technical acceptanceDr. Noura M. Al-Otaibi1 working day overdueAction time limit exceeded · Limit 3 working days

12SCA-PMO-F12Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Not yet · Opens at the «Closure» stage

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close