Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
SCA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
ApprovedPRJ-2026-007SCA Academy Campus, Riyadh

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1Weight and relative weightAuto-filled

Project weight score

89 of 100

Relative weight in the portfolio

⁦27.3%⁩

Portfolio

Academy & Qualification Centres Portfolio

4 projects

Its share of the portfolio’s progress

15.6 points of 38.4%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩525.0
Impact on contractors & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩510.0
Project classificationThe project’s classification⁦10%⁩510.0
Weight score—⁦100%⁩—89

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
SCA Academy Campus, Riyadh89⁦27.3%⁩⁦57%⁩
Jeddah Branch & Qualification Centre82⁦25.2%⁩⁦39%⁩
Hail Vocational Qualification Centre80⁦24.5%⁩⁦52%⁩
Wadi Al-Dawasir Vocational Qualification Centre75⁦23.0%⁩⁦1%⁩
Weighted portfolio progress—⁦100%⁩⁦38.4%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2026-09-16⁩ 09:48
2Weight model complianceMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-17⁩ 11:32
3Portfolio manager approvalTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApproved—⁦2026-09-20⁩ 12:39

Signatures

Weight model compliance

Ghada A. Al-Shahrani

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Abdulrahman S. Al-Harbi

Approved⁦2026-09-20⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦11:32⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2026-09-20⁩ at ⁦12:39⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Noura M. Al-Otaibi

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Noura M. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close